10-07-2004 CHANGE ORDER NUMBER 1, METCALF BASIN DRAINAGE IMPROVEMENTS CONTRACT WITH OLDCASTLE SW GROUP INC DBA B&B EXCAVATING INC TO EXTEND PROJECT ACROSS PROPERTY AT 0077 METCALF ROADMemo To: Honorable Mayor and Town Council Thru: Larry Brooks, Town Manager From: Norman Wood, Town Engineer Date: October 7, 2004 Re: Change Order Number 1, Metcalf Basin Drainage Improvements (Nottingham Road to I-70) Contract with Oldcastle SW Group, Inc. dba B&B Excavating, Inc. to Extend Project Across Property at 0077 Metcalf Road. Summary: Chris and Michelle Evans with Evans Chaffee Construction Group recently purchased the property at 0077 Metcalf Road. They requested that the Town work with them to expedite the Metcalf Storm Drainage Project across this property to allow them to implement some parking and site improvements this fall. This is a natural extension of the Metcalf Basin Drainage Improvements (Nottingham Road to I-70) Project that is currently under construction. The attached Change Order Number 1 to the Metcalf Basin Drainage Improvements (Nottingham Road to I-70) Project adds this work to the current contract with Oldcastle SW Group, Inc. dba B&B Excavating, Inc. The added work includes only that to be provided by the Town per an accompanying Agreement with BBG Holding Corporation (BBG). The corresponding surface finish and site work will be arranged and paid for separately by BBG. This Change Order extends the contract completion date from October 25, 2004 until November 26, 2004 and increases the Contract Amount by $ 153,236.04 from $ 175,989.65 to $ 329,225.69. The proposed Total Project Budget is: Current Proposed Original Construction Contract $ 175,990 $ 175,990 Change Order Number 1 $ -0- $ 153,236 Engineering Design $ 39,900 $ 39,900 Contract Administration $ 10,000 $ 10,000 Testing $ 5,000 $ 5,000 Contingency $ 19,100 $ 21,534 Total Proposed Budget $ 250,000 $ 405,000 1:\Engineering\C1P\Stomiwater Metcalf(Nott To 170)\4.0 Constmction Documents\4.5 Change Orders\Change Order No.I MemO.Doc The Capital Projects Fund Budget as previously presented included $375,000 for this Drainage Project with this addition. If this Change Order is approved the final draft of the Capital Projects Fund Budget will revised to include $405,000 for this project prior to adoption. We recommend approval of the attached Change Order Number 1 to the Metcalf Basin Drainage Improvements (Nottingham Road to I-70) Project Contract with Oldcastle SW Group, Inc. dba B&B Excavating, Inc., extending the completion date to November 25, 2004 and increasing the Contract Amount $ 153,236.04 to $ 329,225.69. This recommendation for approval is in conjunction with a recommendation for approval of corresponding Agreement Governing Design and Construction of Drainage and Site Improvements at 0077 Metcalf Road between the Town of Avon and BBG Holding Corporation. Recommendation: Approve Change Order Number 1 to the Metcalf Basin Drainage Improvements (Nottingham Road to I-70) Project Contract with Oldcastle SW Group, Inc. dba B&B Excavating, Inc., extending the completion date to November 25, 2004 and increasing the Contract Amount $ 153,236.04 to $ 329,225.69. Town Manager Comments: 91'- 0 Page 2 CHANGE ORDER Order No.: One Date: October 12, 2004 Agreement Date: _September 10, 2004 NAME OF PROJECT: Metcalf Basin Drainage Improvements (Nottingham Road to I-70) OWNER: Town of Avon, Colorado CONTRACTOR: Oldcastle SW Group, Inc. dba B&B Excavating Inc. The following changes are hereby made to the CONTRACT DOCUMENTS: Justification: Additional Drainage Improvement installed adjacent to and / or on Lot 22, Block 1, BMBC and TOA right-of-way. Change Order Details: Item 1.1 -Add Mobilization Per Lump Sum 1 LS @ $ $ 4,291.00 Item 1.2 - Surveying / Staking Per Lump Sum 1 LS @ $ $ 4,675.00 Item 1.3 - Pothole Utilities - Coordinating Utility Relocates Per Lump Sum 1 LS @ $ $ 1,550.00 Item 2.1 - Remove and dispose of Ex. CMP Culvert Per Linear Foot 167 LF @ $18.64 $ 3,1 12.88 Item 3.1 - Clearing and Grubbing (including removal and hauling of asphalt) Per Lump Sum 1 LS @ $ $ 1,775.00 Item 3.2 - Site Grading Per Square Foot 14,000 SF @ $0.42 $ 5,880.00 Item 3.4 - Channel Restoration at Outlet (including sediment removal to restore riprap, installation of Fabric, and reshaping bottom of Channel to tie into existing channel) Per Lump Sum 1 LS @ $ $ 5,082.16 Item 6.1 - Install 87" x 63" Pipe Per Linear Foot 225 LF @, $280.58 $ 63,130.50 Item 6.2 - Install Headwall and Drainage Structure at New Culvert Outlet Per Cubic Yard 34.8 CY @ $ 800.00 $ 27,840.00 Item 6.3 - Install Headwall and Drainage Structure at New Culvert Inlet (o) Et ppp Per Cubic Yard 29.6 CY @ $ 800.00 $ 23,656.00 uWU EU V w Or, T 1 2 2004 CO-1 C OMInUnRY ®evel® r~ Item 6.4 - Install Grate at Drainage Structure Inlet Per Each I EA Item 6.5 - Install Grate at Drainage Structure Outlet Per Each 1 EA Item 6.6 - Install D50=18" Rip rap, 36" thick at Inlet Import Materials Only Per Cubic Yard 0 CY Item 6.7 - Install Filter Fabric under riprap Per Square Yard 195 SY Item 7.1 - Erosion Control Silt Fence Per Linear Foot 140 LF Item 7.2 - Traffic Control Per Lump Sum 1 LS Item 7.2 - Install Guardrail Per Linear Foot 0 LS TOTAL @ $ $ 4,400.00 @ $ $ 3,500.00 @ $116.67 $ 0.00 @ $1.30 $ 253.50 @ $3.50 $ 490.00 @ $ $ 3,600.00 @ $ $ 0.00 $ 153,236.04 Change to CONTRACT PRICE: $_153,236.04 Original CONTRACT PRICE: $_175,989.65 Current CONTRACT PRICE adjusted by previous CHANGE ORDER 175,989.65 The CONTRACT PRICE due to this CHANGE ORDER will be (increased)(dee-reased) by . $_153 236.04 The new CONTRACT PRICE including this CHANGE ORDER will be $_329,225.69 Change to CONTRACT TIME: The CONTRACT TIME will be (increased)( by 30 calendar days. The date for completion of all work will be November 24, 20 A (Date). APPROVALS REQUIRED: Approved by Engineer: Accepted by Contractor: Accepted and Approved CO-2