Loading...
22.05.17 PSA RA Nelson LLC Copy-W Exhibits 1 Exhibit A – Preconstruction Services Scope of Work RA Nelson LLC (Contractor) shall participate in preconstruction consulting and price estimating for the Town of Avon (Owner) for the Swift Gulch Employee Housing Project at 500 Swift Gulch Road as outlined below. Project: Construction of four (4) buildings and up to 55-60 units, consisting of a mix of studio, 1-bedroom, and 2-bedroom units with a common driveway branching from the existing transit, fleet, and public works facility, with shared parking facilities, three levels on top of pull-under parking, and shared trash, recycling, compost area. The project is intended to be a rental-only project for public employees on an approx. 2.5 acres site. 1- INITIAL PRELIMINARY EVALUATION The Contractor will provide a preliminary evaluation of the feasibility of the construction of the project based on preliminary project information provided by the Owner, to include an initial analysis of the feasibility of the Owner’s program, schedule requirements, level of finishes and budget for the construction of the project. 2- CONSULTATION The Contractor with the Design Team shall jointly schedule and attend periodic meetings with the Owner. The Preconstruction Manager shall consult with the Owner and Design Team regarding site use and improvements, and the selection of building materials, building systems and equipment and potential alternatives. The Contractor shall provide recommendations on selection of design consultants, construction feasibility; actions designed to minimize adverse effects of labor or material shortages; time requirements for procurement of materials / equipment and factors related to construction costs including estimates of alternative designs or materials, preliminary budgets and po tential cost savings. 3- PRELIMINARY PROJECT SCHEDULE The Contractor shall prepare, and periodically update, a Preliminary Project Schedule for the Design Team’s review and the Owner’s approval. The Owner shall obtain the Design Team’s approval of the portion of the Preliminary Project Schedule relating to the performance of the Design Team’s services. The Contractor shall coordinate and integrate the Preliminary Project Schedule with the services and activities of the Owner, Design Team and Contractor. As design proceeds, the Preliminary Project Schedule will be updated to indicate proposed activity sequences and durations, milestone dates for receipt and approval of pertinent information, submittal of the baseline Cost Control Budget Estimate, preparation and processing of shop drawings and samples, delivery of materials or equipment requiring long -lead time procurement, Owner’s occupancy requirements showing portions of the Project having occupancy priority and / or phasing and estimated date of Substantial Completion. If the Preliminary Project Schedule updates indicate that previously approved schedule dates may not be met, the Contractor shall make recommendations to the Owner and Design Team. 4- DOCUMENT REQUIREMENTS The following paragraphs describe the level the documents need to be completed to at each design phase by the Design Team. It is the responsibility of the Owner and the Design Team to make sure at each phase of the design that the project documents are completed to these standards. This information is required to allow the Preconstruction Manager to complete its work at each phase of the design. 4.1 Schematic Design Documents The Schematic Design Documents shall establish the conceptual design of the Project illustrating the scale and relationship of the project components. The Schematic Design Documents at a minimum shall include a conceptual site plan ( if appropriate ), preliminary building plans, sections and elevations. The Schematic Design Documents may also include study models, perspective sketches, electronic modeling or combinations of these media. Preliminary selections of major building systems and construction materials shall be noted on the drawings or described in writing. 4.2 Design Development Documents The Design Team shall provide Design Development Documents based on the Schematic Design Documents and the updated Schematic Design estimate that has been submitted by the Preconstruction 2 Manager and approved by the Owner. The Design Development Documents shall illustrate and describe the refinement of the design of the Project, establishing the scope, relationships, forms, size and appearance of the Project by means of plans, sections, elevations, typical construction details and equipment layouts. The Design development Documents shall include specifications that identify major materials and systems and establish in general their quality levels. 4.3 Construction Documents Not Applicable 5- PRELIMINARY COST ESTIMATES The contractor shall provide (2) two rounds of pricing with the SD & DD pricing packages and any required value engineering. Upon receipt of the Schematic Design Documents, the Contractor shall prepare, for the review of the Design Team and approval of the Owner, a preliminary Schematic Design Cost Control Budget Estimate utilizing area, volume or similar estimating techniques based on historical cost data. When Design Development Documents have been prepared by the Design Team and approved by the Owner, the Preconstruction Manager shall prepare an estimate with supporting data for review by the Design Team and approval by the Owner. Preconstruction Services associated with the preparation of and cost estimating of the Construction Drawings are excluded from this agreement. If any estimate submitted to the Owner exceeds previously approved estimates or the Owner’s budget, the Preconstruction Manager shall make recommendations to the Owne r and Architect. 6- SERVICES The preconstruction services to be provided hereunder are to facilitate the development of the design by the Design Team and subsequent approval by the Owner. The Contractor is not acting as the designer for the project and shall have no responsibility or liability for designs, specifications or design decisions relating to the Project. The Contractor shall have no responsibility or liability for the accuracy of tests, surveys, soils reports, or other information generated by third parties in connection with the development of the design. Estimates or budgets prepared or reviewed by the Contractor reflect the Contractors’ good faith judgment, based on the information available. The Contractor does not warrant or represent that actual construction costs will be at, below or near such estimates or budgets. Owner and Design Team acknowledge that all such budgets and estimates are created without the benefit of actual bids and quotations being received from subcontractors and suppliers and thus are of limited accuracy. PROJECT:Avon Swift Gulch Employee Housing LOCATION:Avon, Colorado DEVELOPER:Town of Avon DATE:May 17, 2022 Phase No.Personnel Total Start Date Completion Date Project Executive 6 hr $185 /hr $1,110 Project Manager 6 hr $105 /hr $630 Superintendent 0 hr $105 /hr $0 Preconstruction Director 24 hr $195 /hr $4,680 Preconstruction Manager 90 hr $135 /hr $12,150 Estimating Staff 80 hr $85 /hr $6,800 Subtotal SD Phase 206 hr $25,370 Start Date Completion Date Project Executive 8 hr $185 /hr $1,480 Project Manager 8 hr $105 /hr $840 Superintendent 0 hr $105 /hr $0 Preconstruction Director 24 hr $195 /hr $4,680 Preconstruction Manager 110 hr $135 /hr $14,850 Estimating Staff 80 hr $85 /hr $6,800 Subtotal DD Phase 230 hr $28,650 Start Date 6/1/2022 (or date at which the agreement is signed) Completion Date Project Executive 6 hr $185 /hr $1,110 Project Manager 6 hr $105 /hr $630 Superintendent 0 hr $105 /hr $0 Preconstruction Director 16 hr $195 /hr $3,120 Preconstruction Manager 80 hr $135 /hr $10,800 Estimating Staff 0 hr $85 /hr $0 Subtotal Team Meetings 108 hr $15,660 Reimbursables Misc. reimbursables 1 ls $1,500 /ls $1,500 GL Insurance (1%)1%$712 Subtotal Reimbursable:$2,212 TOTAL PRECONSTRUCTION SERVICES (based on RFP schedule):$ 71,892 1/14/2023 EXHIBIT B - PRECONSTRUCTION SERVICES ESTIMATE 1/14/2023 Reoccuring Team Meetings, Assistance w/ Town Approvals, Trend Log Updates Man-hours Cost per Man- hour Cost Schematic Design Phase (Establish Project Goals / Program, Control Budget & Value Engineering) 7/22/2022 9/7/2022 Design Development Phase (DD Estimate & Value Engineering 11/15/2022