L64 B3 WR Design ChangePlanning & Zoning Commission
Staff Report
Submitted for the August 1, 1995 meeting
Date 21 July, 1995
Review Type Final Design
Project Type Change of roof and siding color
Location Lot 64, Block 3 Wildridge
Introduction
The commission approved this project on May 2, 1995, with the condition that it be returned with
a sample of the material and color of the metal roof The applicant now wants to use a brown
(Burnt Chestnut) concrete tile roofing, as well as modifying the wood cedar siding to a semi-
transparent blue -gray (Blue Balsam).
Staff Comments
The material and color of the roof and color of the siding are appropriate according to the design
guidelines, specifically:
1. use of a lower -reflectivity roofing material
2. use of natural or earth -tone colors.
Recommended Action
Approve the roofing color and material, and the siding color, as presented.
If you have any questions regarding this or any other project or community development issue,
please call me at 949-4280 (extension 129), or stop by the Community Development Department.
Respectfully submitted,
George Harrison
Assistant Planner
1.64R3WR nnr
Lot 64, Block 3, Wildridge Subdivision, Final design review, page 2
August 1, 1995 Planning & Zoning Commission meeting
Planning & Zoning Commission Action
R Approved as submitted
❑ Approved with conditions
❑ Denied
❑ Continued
❑ Withdrawn by applicant
Conditions (if applicable)
The Commission approved as submitted.
Date � S Sue Railton, Secretary