TC Res. No. 2005-37 AMEND THE 2005 TOWN OF AVON BUDGETTOWN OF AVON, COLORADO
RESOLUTION NO. 05-37
SERIES OF 2005
A RESOLUTION TO AMEND THE 2005 TOWN OF AVON BUDGET
A RESOLUTION SUMMARIZING EXPENDITURES AND REVENUES AND
AMENDING TVE 2005 CAPITAL PROJECTS FUND BUDGET FOR THE TOWN OF
AVON, COLORADO, FOR THE CALENDAR YEAR BEGINNING ON THE FIRST
DAY OF JANUARY, 2005, AND ENDING ON THE LAST DAY OF DECEMBER, 2005.
WHEREAS, the Town Council of the Town of Avon has adopted the 2005 Capital
Projects Fund budget; and
WHEREAS, the Town Council has reviewed the revised estimated revenues and
expenditures for 2005; and
WHEREAS, the Town Council finds it necessary to amend the 2005 Capital Projects
Fund budget to more accurately reflect the revenues and expenditures for 2005; and
WHEREAS, whatever increases may have been made in the expenditures, like increases
were added to the revenues so that the budget remains in balance as required by law.
NOW, THEREFORE, BE IT RESOLVED BY THE TOWN COUNCIL OF THE TOWN
OF AVON, COLORADO:
Section 1. That estimated revenues and expenditures for the Capital Projects Fund is
revised as follows for 2005:
Original or
Previously
Amended
2005
Budget
Capital Projects Fund
Beginning Fund Balance $ 6,126,149
Revenues and Other Sources • 3,518,935
Expenditures and Other Uses 5,433,616
Current
Proposed
Amended
2005
Budget
$ 6,126,149
3,515,209
3,632,631
Ending Fund Balance 4,211,468 6.008.727
Section 2. That the Capital Projects Fund budget, as submitted, amended, and
hereinabove summarized, hereby is approved and adopted as the capital program budget of the
Town of Avon for the year stated above.
Section 3. That the Capital Projects Fund budget hereby approved, amended, and
adopted shall be signed by the Town Manager and made part of the public record of the Town.
ADOPTED this 11th day of October, 2005.
% ®FTOWN AVON, C ORADO
iISEALI
t : Ronald C. Wolfe, Mayor
ATTEST:
®COR N®0
P C.
Patty Mc e y
Town Cler
2
Capital Projects Fund #41
Amendment #5
- - -
Fund mma
,
Original or
Prev. Amended
Proposed
Difference
Actual
Actual
Budget
Budget
Increase
2003
2004
2005
2005
(Decrease)
REVENUES
Taxes
$ 2,224,452
$ 2,338,060
$ 2,100,000
$ 2,350,000
$ 250,000
Intergovernmental
297,837
200,000
1,049,000
230,290
(818,710)
Investment Earnings
33,699
46,704
63,935
81,419
17,484
Other Revenue
7,987
27,712
16,000
318,500
302,500- _
Total Operating Revenues
2,563,975
2,612,476
3,228,935
2,980,209
(248,726)
Other Sources:
Transfer In from Other Funds
1,186,931
376,069
290,000
535,000
245,000
TOTAL REVENUES
3,750,906
2,988,545
3,518,935
3,515,209
(3,726)
EXPENDITURES
Capital Improvements:
Facilities
-
-
2,120,000
1,168,050
(951,950)
Land and Land Improvements
25,640
244
400,000
150,000
(250,000)
Roads and Streets
307,943
287,199
2,175,000
1,435,000
(740,000)
Recreation
-
-
38,305
30,905
(7,400)
Stormwater and Drainage
1,216,270
376,069
150,000
150,000
-
Development Services
97,837
-
-
-
-
Strategic Planning
18,563
91,120
25,000
284,700
259,700
Other
3,000
-
165,000
195,000
30,000
Developer Rebates
247,076
158,665,
300,000
158,665
(141,335)
Total
1,916,329
913,297
5,373,305
3,572,320.
. (1,800,985)
Other Uses
Operating Transfer-Out to General Fund
200,000
50,000
50,000
50,000
-
Operating Transfer-Out to Wildridge S.I.D.
12,271
11,292
10,311
10,311
-
TOTAL EXPENDITURES 2,128,600 974,589 5,433,616 3,632,631 (1,800,985)
NET SOURCE (USE) OF FUNDS 1,622,306 2,013,956 (1,914,681) (117,422) 1,797,259
FUND BALANCE, Beginning of Year
2,489,887
4,112,193
6,126,149
6,126,149 -
FUND BALANCE, End of Year
4,112,193
$ 6,126,149
$ 4,211,468
$ 6;008,727 $ 1,797,259
Page 1
6
Capital Projects Fund #41
Amendment #5
Original or
Prev. Amended Proposed Difference
Account Actual Actual Budget Budget Increase
Number Description 2003 2004 2005 2005 (Decrease) -
'Taxes: - -
51401 Real Estate Transfer Tax $ 2,224,452 $ 2,338,060 $ 2,100,000 $ 2,350,000 $ 250,000
51000 ' Total Taxes
Intergovernmental:
Federal Grants:
53199
Community Development Block Grant
53199
FTA/CDOT Transportation Center Grant
Local Government(Other Agency:
53401
ERWSD Sewer Line Reimb.
53401
Village at (Avon)
53401
Eaglebend Housing Authority
53000 Total Intergovernmental
Investment Earnings:
57101 Interest Earnings
2,224,452 2,338,060 2,100,000 2,350,000 250,000
97,837
200,000
824,000 - (824,000)
- - 5,290 5,290
200,000 200,000 200,000 -
- 25,000 25,000 -
297,837 200,000 1,049,000 230,190 . -__.--(818,710)-
33,699 46,704 63,935 81,419 17,484
57000 Total Investment Earnings 33,699 46,704 63,935 81,419- - - _ 17,484
Other Revenues:
58102
Utility Capital Facility Fees
444 376
2,000 2,000
-
58104
Fireplace Fees
1,500 -
9,000 9,000
-
58211
Development Reimbursements
4,029 18,328
5,000 192,500
187,500
58211
Eagle River Enhancement Reimbursements
- -
- 107,500
107,500
58211
W. Avon Trails Reimbursement
- -
- 2,500
2,500
58999
Miscellaneous Nonclassified Revenues
2,014 9,008
- -5,000--
5,000
58000 Total Other Revenues
Other Sources:
59201 Transfer In from Other Funds
7,987 27,712 16,000 318,500 302,500
1,186,931 376,069 290,000 535,000 ' 245,000
59000
Total Other Sources
1,186,931
376,069
290,000
535,000
245,000
50000
TOTAL REVENUES
$ 3,750,906 - $
2,988,545 $
3,518,935 $
3,515,209 $
(3,726)
Page 2
1Y
Capital Projects'Fund #41
Amendment #5
- - JO,- .I-o-ects t~n~r~e~to .
Original or
Prev. Amended Proposed Difference
Account Actual Actual Budget Budget Increase
Number Description 2003 2004 2005 2005 (Decrease)
CAPITAL IM_ PRO_ VEMENT PROJECTS
Facilities-
11006
Council Chambers Audio/Video Upgrade $
- $
- $
70,000 $
70,000 $
-
11007
Municipal Building Roof Replacement
-
-
50,000
50,000
-
14001
Transportation Center
-
-
`2,000,000
1,048,050
(951,950)
Land and Land Improvements:
Parks:
21004
Tract J Bridge Removal
25,640
244
-
-
-
21005
Wildridge Park Improvements and Playground
-
-
150,000
150,000
-
21006
Wildridge PocketPark - New Block 3 or 4
-
-
250,000
-
(250,000)
Roads and Streets:
Streetscape:
31006
Eaglebend Dr.
-
-
40,000
50,000
10,000
31008
Nottingham Rd. Imp. / 1-70 to Buck Creek
-
73,694
25,000
25,000
-
31009
Nottingham Rd. Imp. / Buck Creek to Metcalf Rd.
1,902
-
-
-
-
Street Improvements:
32005
Buffalo Ridge Commitments
56,941
-
-
-
-
32007
Town Center-Mall Plan Implementation
-
-
1,200,000
400,000
(800,000)
32008
E. Beaver Creek Blvd. Improvements
-
6,585
-
-
-
Annual Street Improvements:
33003
2003 Paving/Road Improvements
225,650
-
-
-
-
33004
2004 Paving/Road Improvements
-
205,735
-
-
-
33005
2005 Paving/Road Improvements
-
-
865,000
890,000
25,000
Multi-Modal/Altemative Mobility:
34002
East Avon Access and Circulation
18,126
-
-
_
-
34005
Eagle River Bikepath - Beaver Creek Blvd to Conf.
5,324
-
-
-
-
34007
Wildridge Traffic Calming & Pedestrian Circulation
-
1,127
-
-
-
34009
Swift Gulch Road Bikepath Extension
-
58
45,000
45,000
-
34010
Swift Gulch Rd. Bikepath from RA #1
-
-
-
20,000
20,000
34012
West Avon Trails and Access Enhancement
-
-
-
5,000
5,000
Recreation:
51002
Eagle River Whitewater Park, Access & Viewing
-
-
38,305
30,905
(7,400)
Stormwater and Drainage:
61001
Buck Creek / 1-70 to Eagle River
1,216,270
-
-
-
-
61003
Metcalf Rd. Drainage / 1-70 to Nottingham Rd.
-
376,069
-
-
-
61004
Nottingham-Puder-Ditch Restoration
-
-
150,000
150,000
-
Development Services:
65004
Buffalo Ridge
97,837
-
-
-
-
Page 3
Capital Projects Fund #41
Amendment #5
CiP-'9o eats I nVf t f
-
Original or
Prev. Amended
Proposed
Difference
Account
Actual Actual
Budget
Budget
Increase
Number
Description
2003 2004
2005
2005
-(Decvease)_
CAPITAL IMPROVEMENT PROJECTS
Strategic Planning:-
Development Analysis and Review:
71004
Confluence / Westin Riverfront Resort
- -
-
175,000
175,000
71006
Sheraton Mountain Vista 2005 Application
- -
-
17,500
17,500
79001
General Planning and Consulting
18,563 -
-
-
-
79002
Comprehensive Plan
- 82,773
-
67,200
67,200
79004
2004 General Planning and Consulting
- 8,347
-
-
-
79005
2005 General Planning and Consulting
- -
25,000
25,000
-
Other:
91001
Fireplace Conversions
3,000
93005 _
2005 Historic Preservation
- - 25,000 -
(25,000)
93006
Historic Analysis Study
- - - 25,000
25,000
94005
2005 Water Rights Acquisition
- - 140,000 140,000
-
94006
RICD Water Rights Acquisition
- - - 30,000
30,000
Total Capital Improvement Projects
$ 1,669,253 $ 754,632 $ 5,073,305 $ 3,413,655 $
_ (1,659,650)
Page 4