20.09.22 PSA GSG Architecture, Inc
1
EXHIBIT B
On-Call Agreement for Professional Services
TASK ORDER 2-2022-01
Public Works Facility Programming and Site Planning
This Task Order pertains to the On-Call Agreement by and between the Town of Avon
(“TOWN”), and GSG Architecture, Inc. (“CONTRACTOR”), dated On-Call Contract Execution
of September 20, 2022 (“the Agreement”).
CONTRACTOR shall perform services as provided herein and in the Agreement. This Task
Order shall not be binding until it has been properly signed by both parties. Upon
execution, this Task Order shall supplement the Agreement as it pertains to the project
described below.
Project Description: Provide Facility Programming and Site Planning for a Public Works
Facility. See Attachment A
Project Site:
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
2
Proposed Tasks: See Attachment A.
1. Public Works Facility Programming and Site Planning.
Budget/Proposal: ____________$54,983_ _______________________________________
Completion Schedule: __Eight weeks from Notice to Proceed__________________________
This Task Order is as approved by the September 30, 2022 On-Call Agreement on the
11th day of November 2022.
Town of Avon
Recommended:_________________________________Public Works Director ____Date: ______________
Eva Wilson Title
GSG Architecture, Inc.
Approved: _______________________________________Principal_and CEO________ Date: ______________
James Holloway Title
Town of Avon
Approved: __________________________________________Town Manager ____Date: ______________
Eric Heil Title
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
11/11/2022
11/11/2022
11/11/2022
Town of Avon, Colorado
TASK ORDER #1 - Public Works Site Analysis
GSG Architecture Proposal for A & E Services
November 10, 2022
Page 1
Explanation of Fees:
This proposal encompasses the following phases, services and deliverables listed below:
SCOPE OF SERVICES
Existing Site Analysis / Programming
•The GSG Team will meet with Public Works Department Employees and Town administrators to
gather information about the current conditions, growth forecasts and equipment inventories.
•We will review your work protocols and look for ways to increase operational efficiency.
•We will work with you to establish the necessary hierarchies and adjacencies and will provide
diagrammatic documentation of these elements.
•Using this information, we will create an inventory of required spaces and arrive at an optimal
square footage for the facility.
•We will review survey data provided by the Town or another agency.
•Our team will review each site with regards to topography, access, solar orientation and size
(including expansion potential) relative to the requirements of the program study.
•A site plan will address access points, appropriate turn radii for all vehicles, parking areas and
potential for future expansion.
•Massing variations will be provided for analysis. With you, we will design several iterations for
review and consensus. Volume studies will be accomplished in real time with you using Google
Sketchup for quick renderings and massing studies.
•The Scope of Work includes mass and scale studies on two sites including cost estimates.
•Probable development and reconfiguration costs will be examined.
•Our team will prepare a written report detailing the site analysis findings and offering
recommendations for the most efficient configuration capable of supporting a new facility.
•A written opinion of probable cost will be generated based on the report and site plan.
•We will lead a final presentation to the Town administrators, the Public Works Department and
members of the public, (if desired).
Exclusions
•Geotechnical Investigations
•Phase I Environmental Investigations
•Title Search, Financial planning or other activities typically associated with property acquisition
•Topographic site surveys
•Hazardous material investigations reports, and abatement
•Schematic Design, Design Development, Construction Documents phase services (to be
addressed in future task orders)
Attachment A
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
Town of Avon, Colorado
TASK ORDER #1 - Public Works Site Analysis
GSG Architecture Proposal for A & E Services
November 10, 2022
Page 2
Fixed Fee Proposal for Existing Site Analysis / Programming Services $ 52,223
(includes Civil Engineering and Cost Estimating)
Anticipated Expenses (estimate only) $ 2,760
TOTAL $ 54,983
Please call to discuss at your convenience. We are always willing to discuss fee and scope to suit the
best interests of the project.
Sincerely,
James Holloway, AIA, LEED AP
CEO / Principal
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
GSGarchitecture
1 - Review of Existing Site Conditions Hours Rate Amount
Principal 4.0 $225 900.00
Principal Architect 22.0 $195 4,290.00
Project Manager 22.0 $165 3,630.00
Technical Staff 22.0 $105 2,310.00
Administrative Staff 2.0 $95 190.00
1 - TOTAL 72.0 11,320.00
2 - Review of Existing Equipment / Needs Hours Rate Amount
Principal 1.0 $225 225.00
Principal Architect 1.0 $195 195.00
Project Manager 2.0 $165 330.00
Technical Staff 4.0 $105 420.00
Administrative Staff 1.0 $95 95.00
2 - TOTAL 9.0 1,265.00
3 - User and Administration Meetings Hours Rate Amount
Principal 0.0 $225 0.00
Principal Architect 6.0 $195 1,170.00
Project Manager 6.0 $165 990.00
Technical Staff 6.0 $105 630.00
Administrative Staff 1.0 $95 95.00
3 - TOTAL 19.0 2,885.00
4 - Site Plan Design / Final Presentation Hours Rate Amount
Principal 8.0 $225 1,800.00
Principal Architect 4.0 $195 780.00
Project Manager 18.0 $165 2,970.00
Technical Staff 48.0 $105 5,040.00
Administrative Staff 2.0 $95 190.00
4 - TOTAL 80.0 10,780.00
5 - Written Report Hours Rate Amount
Principal 1.0 $225 225.00
Principal Architect 16.0 $195 3,120.00
Project Manager 4.0 $165 660.00
Technical Staff 0.0 $105 0.00
Administrative Staff 8.0 $95 760.00
5 - TOTAL 29.0 4,765.00
6 - Consultant Coordination Hours Rate Amount
Principal 2.0 $225 450.00
Principal Architect 4.0 $195 780.00
Project Manager 12.0 $165 1,980.00
Technical Staff 8.0 $105 840.00
Administrative Staff 2.0 $95 190.00
6 - TOTAL 28.0 4,240.00
SERVICES TOTAL 237.0 35,255.00
Site Analysis / Programming
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
JVA CIVIL ENGINEERS
1.REVIEW OF EXISTING SITE CONDITIONS
Principal $220/hr. 4 hours $ 880
Senior Engineer $144/hr. 12 hours $1,728
SUBTOTAL $2,608
2.REVIEW OF EXISTING EQUIPMENT/NEEDS (No Civil Scope)
3.USER / ADMINISTRATION MEETINGS
Principal $220/hr. 8 hours $1,760
SUBTOTAL $1,760
4.SITE PLAN DESIGN
Principal $220/hr. 4 hours $ 880
Senior Engineer $144/hr. 30 hours $4,320
SUBTOTAL $5,200
5.WRITTEN REPORT (No Civil Scope)
6.CONSULTANT COORDINATION (No Civil Scope)
SUBTOTAL $9,568
Reimbursables $ 232
TOTAL $9,800
GSG Administration $ 980
$10,780
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
KEMP COST ESTIMATION
1.REVIEW OF EXISTING SITE CONDITIONS (no scope necessary)
2.REVIEW OF EXISTING EQUIPMENT/NEEDS (no scope necessary)
3.USER / ADMINISTRATION MEETINGS (no scope necessary)
4.SITE PLAN DESIGN
Principal 10 hours $135/hr $ 1,350
Senior Project Estimator 31 hours $125/hr $ 3,875
Administrative Assistant 8 hours $ $ 50/hr $ 400
SUBTOTAL $ 5,625
5.WRITTEN REPORT (no scope necessary)
6.CONSULTANT COORDINATION (no scope necessary)
GSG Administration $ 563
TOTAL $6,188
DocuSign Envelope ID: 13D8A554-D62F-4584-A40F-8EE7AA3C9EB1
GSG REIMBURSABLES (estimate only)
1.REVIEW OF EXISTING SITE CONDITIONS
Hotel Room in Avon (3 persons) $200 x 3 x 2 nights $ 1,200
6 meals in Avon (3 persons) $40 each $ 720
Mileage to/from Avon 400 miles $ 250
SUBTOTAL $ 2,170
2.REVIEW OF EXISTING EQUIPMENT/NEEDS (included in Review of Site above)
3.USER / ADMINISTRATION MEETINGS (included in Review of Site above)
4.SITE PLAN DESIGN (if necessary)
Additional Site Visit Mileage to /from Avon 400 miles $ 250
Meal in Avon $40 $ 40
SUBTOTAL $ 295
5.WRITTEN REPORT Printing $ 295
6.CONSULTANT COORDINATION (no reimbursables)
TOTAL $2,760