Loading...
25.06.16 PSA Stolfus & Associates1 EXHIBIT B On-Call Agreement for Professional Services TASK ORDER 2.8 US6 Mobility Improvement Project: Design Services During Construction This Task Order pertains to the On-Call Agreement by and between the Town of Avon (“TOWN”), and Stolfus and Associates (“CONTRACTOR”), dated On-Call Contract Execution of September 3, 2021 (“the Agreement”). CONTRACTOR shall perform services as provided herein and in the Agreement. This Task Order shall not be binding until it has been properly signed by both parties. Upon execution, this Task Order shall supplement the Agreement as it pertains to the project described below. Project Description: Provide final design for the US6 Multimodal Safety and Mobility Improvements project. The project received the CDOT Revitalizing Main Street Grant to slow prevailing speed on US6 and potentially install 3 pedestrian crossings as shown on the project site below. Additional funds are needed to design a stormwater drainage system. Project Site: Proposed Tasks: See Attachment A. 1. Design Services During Construction Budget/Proposal: ___$40,000 ____________________________________ Schedule: Performed during the bid process and construction of the US6 Safety and Mobility Project 2 This Task Order shall supplement the September 3rd, 2021 Agreement. Town of Avon Recommended: ________________________________Engineering Director ____Date: ______________ Eva Wilson Title Stolfus and Associates Approved: ________________________________________President________________ Date: ______________ Elizabeth Stolfus Title Town of Avon Approved: ______________________________________Town Manager ___________Date: ______________ Eric Heil Title Eva Wilson (May 16, 2025 16:51 MDT)05/16/2025 05/16/2025 Eric Heil (May 20, 2025 16:48 MDT) Eric Heil 05/20/2025 5690 DTC Boulevard, Suite 330W Greenwood Village, CO 80111 Phone: 303-221-2330 * fax: 303-221-2331 www.stolfusandassociates.com April 18, 2025 Eva Wilson, PE, PTOE, CFM Engineering Director Town of Avon ewilson@avon.org Re: Scope of Work for 24776 - Avon US6 Mobility - Design Services During Construction Dear Eva, The Avon US 6 Mobility project is located on US 6 in the Town of Avon. The project starts at River Edge Apartments (MP 169.5) and ends at Eagle-Vail Rd (MP 171.0). The Town of Avon identified a need to address safety and pedestrian mobility concerns on US 6 due to the lack of pedestrian crossings in the project area. The identified need will be addressed through this project by providing traffic calming through the corridor to facilitate the addition of multimodal safety improvements, including pedestrian crossings at transit stops. Through a previous contract with Stolfus & Associates, Inc. (Stolfus), final design for the corridor was completed. Stolfus is pleased to provide services for the Avon US 6 Mobility construction project. The following services are included in the scope: • Design Services During Construction The following describes the proposed scope of services necessary to accomplish the above task: SCOPE OF SERVICES Project Administration/Management Stolfus will review and process invoices monthly and provide other project administration/ management services (coordination and product review) throughout the duration of the project. Stolfus will be responsible for day-to-day management and coordination of the work elements. This will include coordination on Requests for Information (RFIs), plan revisions, and submittal reviews. Celeste Shinn will be the primary point of contact throughout construction. Roadway and Traffic Design Services During Construction (Stolfus) Construction Meetings It is assumed that Stolfus will attend the following meetings: • Construction team meetings – assume 1 hour meeting per month for up to eight (8) meetings (virtual) • Pre-Construction meeting – one (1) (virtual) Requests for Information Stolfus will review and respond to the Contractor’s requests for information (RFIs). All RFIs must be submitted by the Contractor in writing. Stolfus will review and respond in writing within one week after receiving a written RFI. Up to five (5) RFIs are included in this scope of services related to roadway and traffic elements. Scope of Work for 24776 - Avon US6 Mobility - Design Services During Construction April 18, 2025 Page 2 Construction Conflict Resolution and Plan Revisions Stolfus will prepare design plan revisions for conflicts that occur during construction, including unknown or changed conditions which require additional analysis, design, and/or plan revisions. Stolfus will provide and seal the revised plans, as necessary and requested by the Town. This scope of work includes: • Plan Revisions – up to three (3) sheets • Specification Revisions – up to two (2) specifications Advertisement Support Stolfus will assist with responding to Contractor’s questions during Advertisement for up to four (4) hours related to roadway and traffic elements. Drainage Design Services During Construction (RESPEC) Post Design Services Post-design services will include reviewing and responding to contractor RFIs, reviewing shop drawings, bid support, and construction conflict resolution and plan revisions. RESPEC anticipates reviewing approximately 5-6 materials submittals based on the AD-level design. Design changes will be shown on revised plans as necessary. RESPEC will be responsible for revisions, submittals, RFIs, and bid support for drainage items pertaining to the HYDR and SWMP sheets of the AD set only. Services up to 54 hours for a total of $7500 are included in this scope of work. Landscaping and Irrigation Design Services During Construction (DHM) Post Design Services DHM will provide construction period services throughout the completion of construction. Services included: support during bidding, reviewing landscape and irrigation product submittals, assist with reviewing and responding to Requests for Information (RFI’s), and minor plan revisions as requested. Services up to $5000 are included in this scope of work. Lighting Design Services During Construction (Clanton & Associates) Post Design Services • Up to four (4) team meetings (virtual) • Up to two (2) minor plan revisions • Review lighting equipment submittals (up to two (2) reviews included) • Review electrical equipment submittals (up to two (2) reviews included) • Respond to RFIs, up to four (4) hours or two (2) RFIs • Respond to bidder questions Survey and ROW Design Services During Construction (Farnsworth) Field Survey Work a. Check existing control points for damage or movement i. It is assumed that the control is in good condition and no other points will need to be set. b. Set up to 8 permanent easement monuments for PE-1 and PE-2. Right-of-Way (ROW) Services: a. Revise the existing right-of-way plans noting the type of monument set and adding the recording information to the Property Tabulation sheets. Scope of Work for 24776 - Avon US6 Mobility - Design Services During Construction April 18, 2025 Page 3 b. Create mylar copies of the revised ROW plans. i. Fill out Eagle County Land survey plat deposit form c. Deposit the mylar plans at the Eagle County Engineering Department. Two trips are assumed. One for setting the monuments and one for depositing the plans. Exclusions The following items are excluded from this scope of work and are expected to be completed by others. • Pre-bid Meeting • Revisions under Ad • Permitting • Public Involvement • Value Engineering services • Inspection Services • Construction Management • Construction As-builts • Weekly Construction Meetings • Utility coordination, support, and inspection • Field SWMP support / Erosion Control Supervisor • Schedule Reviews • Equipment procurement • Commissioning • Subsurface Utility Engineering • Appraisal Staking Schedule and Estimated Fee We are available to begin work on this project immediately upon Notice to Proceed. We will provide the services described above on a Time and Materials basis at our Standard Hourly Rates with a “Not to Exceed” limit which we will not charge beyond with prior written approval. Stolfus has estimated that the above scope of services could be completed for a “Not to Exceed” budget of $40,000 with the following breakdown by discipline: Stolfus (Roadway/Traffic/PM): $14,700 Respec (Drainage/SWMP): $ 7,500 DHM (Landscaping/Irrigation): $ 5,000 Clanton (Lighting): $ 5,000 Farnsworth (Survey/ROW): $ 7,800 Total: $40,000 Invoices for professional services rendered and expenses incurred will be prepared monthly. Invoices will include a detailed description of meetings attended, work in progress, and tasks completed. Scope of Work for 24776 - Avon US6 Mobility - Design Services During Construction April 18, 2025 Page 3 Thank you again for the opportunity to work together on this project. Please call me if you have any questions. Best Regards, STOLFUS & ASSOCIATES, INC. Michelle Hansen, PE Vice President Consulting Services 1-Task Order 2.8-US6 Improvements-Design Services During Construction Final Audit Report 2025-05-20 Created:2025-05-16 By:Eva Wilson (ewilson@avon.org) Status:Signed Transaction ID:CBJCHBCAABAAw7SQUfp-ixOgQf-Dslg6CY8xcPYVSOCk "1-Task Order 2.8-US6 Improvements-Design Services During C onstruction" History Document created by Eva Wilson (ewilson@avon.org) 2025-05-16 - 10:49:21 PM GMT Document emailed to Eva Wilson (ewilson@avon.org) for signature 2025-05-16 - 10:50:53 PM GMT Document e-signed by Eva Wilson (ewilson@avon.org) Signature Date: 2025-05-16 - 10:51:04 PM GMT - Time Source: server Document emailed to Elizabeth Stolfus (elizabeth@stolfusandassociates.com) for signature 2025-05-16 - 10:51:08 PM GMT Email viewed by Elizabeth Stolfus (elizabeth@stolfusandassociates.com) 2025-05-17 - 1:32:10 AM GMT Document e-signed by Elizabeth Stolfus (elizabeth@stolfusandassociates.com) Signature Date: 2025-05-17 - 1:32:41 AM GMT - Time Source: server Document emailed to eheil@avon.org for signature 2025-05-17 - 1:32:43 AM GMT Email viewed by eheil@avon.org 2025-05-20 - 10:47:37 PM GMT Signer eheil@avon.org entered name at signing as Eric Heil 2025-05-20 - 10:48:04 PM GMT Document e-signed by Eric Heil (eheil@avon.org) Signature Date: 2025-05-20 - 10:48:06 PM GMT - Time Source: server Agreement completed. 2025-05-20 - 10:48:06 PM GMT