22.09.27 PSA Stolfus & AssociatesEXHIBIT B On-Call Agreement for Professional Services TASK ORDER 2.2 US6 Mobility Improvement Project: Final Design This Task Order pertains to the On-Call Agreement by and between the Town of Avon (“TOWN”), and Stolfus and Associates (“CONTRACTOR”), dated On-Call Contract Execution of September 3, 2021 (“the Agreement”). CONTRACTOR shall perform services as provided herein and in the Agreement. This Task Order shall not be binding until it has been properly signed by both parties. Upon execution, this Task Order shall supplement the Agreement as it pertains to the project described below. Project Description: Provide preliminary engineering and concept analysis for the US6 Multimodal Safety and Mobility Improvements project. The project received the CDOT Revitalizing Main Street Grant to slow prevailing speed on US6 and potentially install 3 pedestrian crossings as shown on the project site below. Project Site: Proposed Tasks: See Attachment A. 1. Final Design Plans for the roundabout and 3 pedestrian crossings. Budget/Proposal: ___$252,950 ____________________________________ Schedule: __Advertise in_January 2023______________________________________ DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E This Task Order is as approved by Town Council on the 13th day of September, 2022. Town of Avon Recommended: ________________________________Public Works Director ____Date: ______________ Eva Wilson Title Stolfus and Associates Approved: ________________________________________President________________ Date: ______________ Elizabeth Stolfus Title Town of Avon Approved: _________________________________________Avon Town Mayor ____Date: ______________ Sarah Smith Hymes Title Town of Avon Attest: ______________________________________________Avon Town Clerk ____Date: ______________ Patty McKenny Title DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E 9/27/2022 9/27/2022 9/28/2022 9/28/2022 5690 DTC Boulevard, Suite 330W Greenwood Village, CO 80111 phone:303-221-2330 • fax: 303-221-2331 www.stolfusandassociates.com September 6, 2022 Eva Wilson, PE, PTOE Public Works Director Town of Avon EWilson@Avon.org Dear Eva: Stolfus & Associates, Inc. (Stolfus) is pleased to amend our proposal to include additional design support for the roundabout about at US 6 and Stone Bridge Road and for three separate pedestrian crossings to serve adjacent bus stops at River Edge Crossing, Eaglebend Crossing, and Mountain Stream Crossing. Stolfus has completed the conceptual and preliminary design and received support from CDOT to advance to final design. This scope of services will include final design for the roadway and traffic elements, as well as final design for drainage, lighting, and structures and support for ROW exhibits and SUE investigations. It is our understanding the project is funded through a Revitalizing Main Streets grant administered by CDOT and will follow the CDOT Local Agency process. In addition, the project is located on a US Highway, so CDOT design standards will apply. Compliance with CDOT Local Agency process, CDOT standards, and coordination with CDOT staff is included in the scope of services. Geotechnical, Pavement Design, Environmental, ROW Acquisition, Advertisement Support, and Construction Management services are not included in this scope of services. SCOPE OF SERVICES The anticipated scope of services and deliverables for this project include: 1. ROW Exhibits 2.SUE Investigation and Utility Coordination 3. Final Design a.Final (90%) Design Plans and specifications b.Structure selection memo c.Final drainage report d.Conduct a Final Design FOR Review meeting with CDOT (virtual) 4. PS&E a.PS&E documents for approval and clearances for CDOT b. AD documents ELEMENTS OF THE SCOPE OF SERVICES A. PROJECT MANAGEMENT Stolfus will review and process invoices and provide other project administration/ management services (coordination and product review) throughout the duration of the project. Stolfus will be responsible for day-to-day management and coordination of the work elements. Monthly schedule, budget and project status reports will be included in the invoices. Stolfus will maintain the project design schedule. The schedule will be updated as necessary during the design process. Stolfus will notify the Town when tasks are falling behind schedule. Attachment A DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E Eva Wilson, PE, PTOE September 6, 2022 Page 2 The following project team meetings are included in the scope of work:  FOR plan review meeting (virtual)  Up to 4 other progress meetings to address design elements and/or ROW needs Stolfus will be responsible for scheduling the meetings, preparing meeting exhibits, and participating in the meetings. Meeting notes will be generated and distributed to the meeting attendees by Stolfus. B. TRAFFIC ANALYSIS AND CONCEPTUAL DESIGN This work element was completed in the original design task order. No further work is anticipated. C. PRELIMINARY DESIGN This work element was completed in the original design task order. No further work is anticipated. D. PRELIMINARY DESIGN (FIR) PLANS This work element was completed in the original design task order. No further work is anticipated. FINAL DESIGN (FOR) PLANS Stolfus will respond to FIR comments and prepare FOR level plans, specifications and an opinion of probable cost. General conditions are excluded from this scope of services. A CDOT Form 463 (Design Data) will be prepared and submitted to CDOT. Curb ramps will be detailed according to ADA standards. Designs will be refined. Stolfus will provide QA/QC review for the project. Signing and striping plans will be prepared with up to 6 special sign layouts. Phasing and traffic control device plans are excluded from this scope of services. A high- level construction schedule will be prepared to determine a number of working days for the Construction Contract. A memo and an exhibit with plan and profile for the modified driveway at River Forge will be prepared and submitted to CDOT to support Access Permitting to be completed by CDOT. CDOT permitting is excluded from this scope of work. We will also provide technical support throughout the project in an advisory capacity. Our review efforts will confirm appropriateness of methodologies used, accuracy of documents, reasonableness of conclusions, document completeness, and overall clarity. The Final (90%) FOR Submittal will include: - Title Sheet, Standard Plans List, General Notes, Tabulations, Typical Sections, Survey Control Diagram, Geometric Control Plans, Removal Plans, Roadway Plans, Roadway Profiles, Roadway Details, Signing and Striping Plans, Traffic Control Tabulation, Utility Plans, Drainage Plans and Profiles, Lighting Plans, Structure Plans, and Cross-sections PS&E DOCUMENTS The final design will incorporate comments from the FOR and consist of final plans, specifications, and engineer’s opinion of probable cost. The PS&E plan package will be submitted to in electronic (PDF) format for the Town to reproduce for advertisement. E. TOWN OF AVON AND CDOT PLAN REVIEW Stolfus will submit plans to the Town and CDOT for formal review at 30% completion level. Reviews are approximately three (3) weeks. A formal FOR meeting will be held with the Town and CDOT to review the plans. Comments will be summarized and a response matrix will be prepared. F. DESIGN STANDARDS Drawings and designs will be in accordance with the Section 7.32 Engineering Improvement Standards of the Town’s Municipal Code, CDOT Roadway Design Guide, NCHRP Report 672- Roundabouts: An Informational Guide; MUTCD, CDOT M&S Standards, CDOT Standard Specification for Road and Bridge Construction and other standards incorporated by reference. G. FIELD SURVEYS & SUE Farnsworth completed a topographic survey and existing ROW verification for the project as part of the original task order, including the additional survey needed for the driveway modification at River Forge. Farnsworth Group, Inc. will provide SUE services including QL-B locates at the Stone Bridge intersection and an estimated DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E Eva Wilson, PE, PTOE September 6, 2022 Page 3 ten potholes for the project. A utility exhibit and report will be included. Utilities at other sites will be located, but not at a QL-B level. As subconsultant to Stolfus, Farnsworth will complete the following: H. RIGHT OF WAY Approximate permanent and temporary impacts to ROW were defined as part of preliminary design for each site. Final design efforts will look to eliminate or minimize ROW needs. Farnsworth will research existing boundary information and existing plats. Up to 2 title commitments will be ordered to establish existing easements. Farnsworth will draw up any recorded easements in title work. Farnsworth will prepare two temporary easement exhibits and legal descriptions for the two condominium properties east of Stone Bridge (River Forge) and up to an additional two permanent easements for improvements outside the ROW at the eastbound bus stop at Stone Bridge and the westbound bus stop at River Edge. Right-of-way plans and a ROWPR are excluded from the scope of services based on information provided by the CDOT R3 ROW Unit. I. UTILITY COORDINATION Stolfus will provide overall utility coordination/management for the project. Stolfus will coordinate with the SUE provider, review SUE plans and reports as completed and evaluate proposed design with existing utilities to identify impacts. Stolfus will work with the hydraulics and structures designers to develop a utility conflict matrix that will be updated as information is provided from the SUE investigation. Stolfus will assist in developing a testhole plan based on the utility conflict matrix and will coordinate with the SUE provider to obtain testhole information. Stolfus will also develop utility plans to accompany the utility conflict matrix that will identify conflicts, relocations, and responsible parties and will be incorporated into the plan set. Stolfus will hold up to 2 Utility Coordination Meetings with the Town, CDOT and affected utility companies to review impacts and relocations (one virtual and one in-person meeting). The in-person meeting will be scheduled such that only one day is required to meet with all utility owners. Additional one-on-one contacts via phone and email will be provided to coordinate relocation plans, estimates and agreements. Stolfus will work with the individual utility owners to develop utility agreements. Stolfus will also complete the utility specification that outlines the utility impacts and actions by the contractor and/or utility company. J. DRAINAGE AND WATER QUALITY RESPEC will provide hydrology, hydraulics and water quality design for roundabout improvements at US 6 and Stone Bridge Road and at 3 proposed pedestrian crossings along US 6. Permanent water quality improvement features will be incorporated at Stone Bridge Road roundabout site but it is assumed that water quality for the pedestrian crossings will not be required. A stormwater management plan will be developed for the entire project. The Eagle River floodplain is a FEMA Zone AE floodplain which flows parallel to US 6, but it is contained within the existing channel and the proposed project limits are outside of the floodplain limits. Eagle River floodplain permitting is not anticipated and excluded from the scope of work. The FOR phase will build on the analysis from the FIR phase. In addition to refined analysis from the FIR phase, the plans, the SWMP, hydraulic report, and quantities will include additional detail. Storm profiles will be incorporated into the plan set at this phase. PSPs and non-standard details will be added, if necessary. The PS&E phase will build on the analysis from the FOR phase. The plans, SWMP, hydraulic report, PSPs will be finalized and prepared for bid. RESPEC FOR Plan Sheets:  Tabulation of Drainage Structures  Drainage Plan Sheets  Storm Sewer Profiles  Detail Sheets  Stormwater Management Plan Narrative & Plan Sheets J. STRUCTURE DESIGN A small 3-4’ landscape wall is anticipated at the Stone Bridge roundabout on the south side of the roundabout. San Engineering will prepare a structure selection memo for review and acceptance by CDOT. The report will DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E Eva Wilson, PE, PTOE September 6, 2022 Page 4 recommend a feasible wall system for the location and conditions that is consistent with the Town’s desired aesthetics. Geotechnical data will not be collected since it is expected to be a small landscape wall. At FOR structural plans and details will be prepared as well as any project specifications for the landscape wall. Revisions will be made for advertisement, as appropriate. K. LIGHTING DESIGN Clanton and Associates will prepare the lighting and electrical consulting for the following: 1. Roundabout at US6 & Stone Bridge Road 2. Street Lighting 3. Pedestrian Lighting 4. Electrical for Lighting and Rapid Flashing Beacon 90% Final Design (FOR) • Kickoff meeting • Attend one (1) site visit to observe existing conditions • Establish basis of design • Lighting design • Final lighting layout • Luminaire selection • Photometric (point-by-point illuminance) calculations to confirm CDOT compliance • Lighting details • Luminaire schedule • Power Source Locations • Utility coordination • Electrical design • Panel schedules • One line diagrams • Lighting Control Centers, including short circuit calculations and feeder sizing • Circuiting and conduit, including voltage drop calculations and conduit sizing • Electrical details • Specifications (CDOT format) • Tabulation of Approximate Quantities • Opinion of Probable Cost • Up to one (1) submittal (90% set) • Quality Control • IDR of submittal • Up to three (3) design meetings • Attendance at 90% Review meeting by web conference 100% Bid Set (PS&E) • Incorporate comments from FOR review, up to one (1) comment response • Final lighting design • Final electrical design • Final specification revisions (CDOT format) • Tabulation of Approximate Quantities • Opinion of Probable Cost • Up to two (2) submittals • Quality Control • IDR of submittal • Stamp set • Up to one (1) design meeting Specific exclusions from this scope are as follows: DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E Eva Wilson, PE, PTOE September 6, 2022 Page 5 • Electric Vehicle (EV) electrical infrastructure design • Electrical receptacles for holiday lighting or maintenance • Electrical engineering for additional electrical devices not listed • Significant lighting and/or electrical redesign after resolution of 30% comments provided by Town of Avon and CDOT submittal based on client changes such as: changes in streetlight • ownership, addition of new electrical service(s), or a change from resetting existing streetlights to new streetlight installation. • Smart city and/or small cell infrastructure • Any development, design, or detailing of custom luminaires • Equipment procurement • Commissioning K. CONTRACT TIME Stolfus will complete the scope of services by February 2023, excluding CDOT review and approval for advertisement. L. DESIGN SUPPORT DURING CONSTRUCTION This scope of services excludes advertisement and design services during construction. M. PUBLIC INVOLVEMENT SUPPORT No further public involvement is included in this scope. DELIVERABLES Deliverables expected for this project include meeting notes; ROW exhibits, SUE plans; design calculations; drainage report, structure selection memo; Final (90%) plans, quantities and opinion of probable cost; PS&E documents and comment response matrix; in electronic format. FEE Stolfus and its subconsultants will perform these engineering services for an additional fee of $252,950 for a total project cost of $400,000. We appreciate the opportunity to work with the Town of Avon and would be happy to answer any questions you have on this Scope of Services. Sincerely, STOLFUS & ASSOCIATES, INC. Michelle R. Hansen, PE Senior Transportation Engineer DocuSign Envelope ID: 180FBF5F-F8EC-441A-B9BB-45B7FA292C7E