25.10.10 SCA Baker Builders, LLC CO-6 Form Approved by Town Attorney – 05/15/2024 CHANGE ORDER Order No.: 006 Date: October 10, 2025 Agreement Date: November 25, 2024 NAME OF PROJECT: East Nottingham Park Improvements OWNER: Town of Avon, Colorado CONTRACTOR: __Baker Builders, LLC dba Baker Constructors The following changes are hereby made to the CONTRACT DOCUMENTS : Justification: This change order captures additional fees for an added paver color, electrical service rerouting, and revisions for a seat wall foundation conflict. Attachment A summarizes the revised plan quantities, resulting in a total contract adjustment of $25,009.00. None of adjustments herein result in a change to the contract time. CONCRETE PAVERS ($4,969): Plan Sheet L1.0 detailed the Concrete Pavers as a 3-tone Brown color mix. Upon Further investigation, the colors palate that matches the adjacent Avon Performance Pavilion is a blend of the 3-tone brown and the Sierra Brown. The additional color was added to the contract with a cost addition from the supplier for an additional color palate as detailed in Baker PCO_020 Attachment B. This adds Line Item 35a: Concrete Paver Color at $4,969 LS to the contract amount. ELECTRICAL-PLAYGROUND BATHROOM SERVICE REROUTE ($16,688): Avon directed the electricians to utilize the existing conduit under the recreation path and irrigation ditch to rerouting the secondary electrical service to the HAN Nottingham Playground Bathroom in order to minimize excavation impacts in these areas. The unintended impact of that direction was a required large service panel with a disconnect and meter installed next to the transformer, playground, and recreation path. To mitigate this impact, Avon requested that service be re-run in an uninterrupted conduit from the transformer to the restroom building to allow the meter and disconnect to be installed on the backside of the building in a lower visibility location. Baker PCO 021, Attachment C, details the costs associated with this scope. This adds Line Item 53b: Playground Bathroom Service Reroute at $16,688 LS to the contract amount. SEATWALL MODIFICATION ($3,352): A Water Line Manhole and Vent Pipe encroach into the alignment of the seat wall foundation. RFI 18 provides a solution to flip and overlap the footer as well as lower it to encase the vent pipe. The costs for this additional excavation, forming, materials, and labor are detail in Baker PCO 022, Attachment D. This adds Line Item 79a: Seat Wall Modification at $3,352 LS to the contract amount. CO-6 Form Approved by Town Attorney – 05/15/2024 Change to CONTRACT PRICE: $ 25,009.00 Original CONTRACT PRICE: $ 3,940,836.00 Current CONTRACT PRICE adjusted by previous CHANGE ORDER $ 4,032,617.76 The CONTRACT PRICE due to this CHANGE ORDER will be increased by $ 25,009.00. The new CONTRACT PRICE including this CHANGE ORDER will be $ 4,057626.76. Change to CONTRACT TIME: The CONTRACT TIME will be (increased)(decreased) by 0 calendar days. The date for completion of all work will be May 20, 2026. APPROVALS REQUIRED: Approved by Engineer: Nicole Mosby, Avon Senior Engineer Accepted by Contractor: Terry Been, Baker Director of Construction Accepted and Approved by Owner: Eva Wilson, Avon Engineering Director Federal Agency Approval (where applicable): __________________ Nicole Mosby (Oct 10, 2025 11:44:58 MDT) Nicole Mosby Terry W Been (Oct 17, 2025 13:44:18 MDT) Terry W Been Eva Wilson (Oct 19, 2025 16:50:50 MDT) CO-6 Form Approved by Town Attorney – 05/15/2024 Attachment A ITEM DESCRIPTION East Notthingham Park (Base Bid) UNIT QUANTITY UNIT PRICE TOTAL PRICE TOTAL – BASE BID 3,940,836.00$ CHANGE ORDER #1 8 Sawcut Asphalt Material LF 122 7.30$ 890.77$ 16 Excavation CY 8 138.77$ 1,110.13$ 18 Export CY 8 21.87$ 174.93$ 31 2' wide Concrete Curb & Gutter (Incl. Base Course) LF 122 58.51$ 7,138.17$ 66 Deciduous Shrubs - 5 Gal. EA -6 1,168.00$ (7,008.00)$ 72 River Rock Cobble Mulch - 3" Depth SF -88 7.30$ (642.40)$ 73 Kentucky Bluegrass Seed SF -21832 0.37$ (7,969.00)$ 74 Native Seed SF 21832 0.37$ 7,969.00$ 87 Sawcut Asphalt Material LF -20 7.30$ (146.00)$ 89 Aggregate Road Base, Cl 6 TN -94 36.50$ (3,431.28)$ 90 Asphalt (Grading SX PG 58-28) TN -64 109.51$ (7,008.48)$ 91 Install UM-30S Electric Vault EA 1 5,548.00$ 5,548.00$ 92 Electric Primary Trenching w/ Conduit* LF -161 461.10$ (74,236.66)$ 93 Connect to Existing RR Bore Conduit LS -0.9 18,971.11$ (17,074.00)$ 98 Exterior Finishes LS 1 3,169.30$ 3,169.30$ 99 Foundation (per structural plans) LS 1 13,973.58$ 13,973.58$ 102 Foundations (Shade Canopy) LS 1 2,618.18$ 2,618.18$ TOTAL – CHANGE ORDER #1 (74,923.75)$ CHANGE ORDER #2 46 Relocate FH & Gate Valve LS 1 7,855.00$ 7,855.00$ 94a Lake Street Overexcavation & rework LS 1 22,617.00$ 22,617.00$ 82 Moveable Bike Racks EA -4 1,423.75$ (5,695.00)$ TOTAL – CHANGE ORDER #2 24,777.00$ CHANGE ORDER #3 7 Trees EA 10 730.09$ 7,300.90$ 37 Striping (4" White) LF -312 2.38$ (742.56)$ 38 Thermoplastic Pavement Marking SF -20 24.50$ (490.00)$ 48 4" SDR35 Sewer Service w/ CO LF 68 248.22$ 16,879.00$ 48a 4" SDR35 Sewer Service MH Drop to Invert (wye & 45 Bends) LF 16 248.22$ 3,972.00$ 42b Pothole 2 additional utilties EA 2 825.00$ 1,650.00$ 58b Extended Confined Space Entry HR 3 100.00$ 300.00$ 93a Deep Excavation EA 1 16,480.00$ 16,480.00$ 93b Testing of Deep Excavation (Allowance) HR 16 85.00$ 1,360.00$ 42a Surveying (Staking and As-builts Location) HR 3 391.25$ 1,174.00$ 103a Margin and Overhead (5% on non-contract line items) LS 1 1,049.00$ 1,049.00$ TOTAL – CHANGE ORDER #3 48,932.34$ CHANGE ORDER #4 104 Remove and Replace Waterfountains (as specified in plans) LS 4 22,131.75$ 88,527.00$ 105 Rock Cobble (N Park Restroom) EA 1 200.00$ 200.00$ TOTAL – CHANGE ORDER #4 88,727.00$ CHANGE ORDER #5 14a Disposed of Additional Debris EA 1 547.00$ 547.00$ 37 Striping (4" White) LF -753 2.38$ (1,792.14)$ 53a Splice Credit LS 1 (12,403.00)$ (12,403.00)$ 83a Bi-level water fountain with bottle filler (including connection) EA 2 7,330.50$ 14,661.00$ 97a Plumbing Drawings Scope LS 1 32,303.00$ 32,303.00$ 66 Deciduous Shrubs - 5 Gal. EA -34 1,168.00$ (39,712.00)$ 67 Coniferous Shrubs - 5 Gal. EA -3 1,095.00$ (3,285.00)$ 68 Ornamental Grasses - 5 gal. EA -51 36.50$ (1,861.72)$ 69 Perennials - 1 Gal. EA -347 21.90$ (7,599.97)$ 74a Replace Seed with Fescue Sod LS 1 16,592.00$ 16,592.00$ 99a Welding LS 1 7,320.00$ 7,320.00$ 103b GC Overhead - Site Trailer Power Connection Credit Month 5 (100.00)$ (500.00)$ TOTAL – CHANGE ORDER #5 4,269.17$ CHANGE ORDER #6 35a Concrete Paver Color LS 1 4,969.00$ 4,969.00$ 53b Playground Bathroom Service Reroute LS 1 16,688.00$ 16,688.00$ 79a Seat Wall Modification LS 1 3,352.00$ 3,352.00$ TOTAL – CHANGE ORDER #6 25,009.00$ TOTAL – CONTRACT PRICE w/ COs 4,057,626.76$ East Park Change Order 6 Summary Baker Construction CO-6 Form Approved by Town Attorney – 05/15/2024 Attachment B August 26, 2025 Baker Constructors 5660 Iris Parkway Frederick, CO 80504 Attn:Terry Been PROPOSED CHANGE ORDER #1 RE:East Nottingham Park Improvements Avon, CO 81620 Dear Terry, Masonry revisions: 1)$4,615.00 Total Additional Cost $4,615.00 Notes: 1. Please confirm sizes are Plaza Rectangle, Plaza Square, Giant Plaza Rectangle, and Plaza II. BERICH MASONRY MOUNTAIN DIVISION Eric Peterson President Material price increase for addded paver color. CO-6 Form Approved by Town Attorney – 05/15/2024 Attachment C Baker Constructors 5560 Iris Parkway Frederick, CO 80504 720.491.3427 Project Name: TOA - East Nottingham Park Date: 10/7/2025 Baker Project #:24-1037 Source: PCO# 021 Initiating Document:Revised Utility Dwg CP Description:NE Bathroom Service Rework Schedule Impact:No Scope Description: Remove existing switchgear Install new conduit from transformer to tie in point on south side of creek Mount service gear to North wall of Restroom Excludes: recessing the conduit, etc in the wall of the restroom, all gear to be surface mounted. Add Amount: $16,688.00 Cost Code: Subcontractor Name: Description: Qty Unit Price Amount: 31.100 Tri Phase Rework Electrical Service to bathroom 1 LS 15,498 Rounding 1 0 - 15,498 Margin & Overhead (5%) 775 Subtotal 16,273 130 285 16,688 Baker Constructors Town of Avon Signature Signature Terry Been Nicole Mosby Print Name Print Name Director of Construction Town Engineer Title Title Date Date Notwithstandingany provisionto the contrary, by signing this Change Request,Owner represents and agrees that : (1) Owner approves the pricing set forth herein; (2) this Change Requet shall automatically become part of the Contract Documents; (3) Baker and/or its subontractors and/or suppliers are directed to proceed with the changed and/or extra work defined herein and the supporting documentation; (4) Owner is obligated to pay for such work in accordance with the Contract Documents; and (5) Contractor is not responsible for any design errors or omissions resulting from such change. 07-Oct-25 CHANGE PROPOSAL Total COST BREAKDOWN Cost of Work Insurance Premium(.9%) P&P Bond Premium(1.75%) PROPOSAL DATE 9/25/2025 PROPOSAL NO. 5758 NAME / ADDRESS Baker Constructors, LLC 5660 Iris Pkwy Frederick, CO 80504 Tri Phase Electric Company 0325 Hardscrabble Road Gypsum, CO 81637 Phone (970) 524-7135 PROJECT East Nottingham If you have any questions or if we can be of further assistance, please call. Thank You.TOTAL DESCRIPTION QTY COST TOTAL Scope of Work: North Bathroom Service Demo 1. Demo existing electric service conduit and conductors installed at HCE transformer Journeyman 8 105.00 840.00 Backhoe 2 175.00 350.00 2. Dismantle disconnect and electric meter from unistrut rack at HCE transformer and relocate to north bathroom building exterior panel Journeyman 32 105.00 3,360.00 Backhoe 4 175.00 700.00 3. Re-excavate existing 2" sleeve on south side of creek and trench to electric panel on north side of bathroom building Journeyman 8 105.00 840.00 Backhoe 4 175.00 700.00 4. Excavate and backfill HCE transformer and stub new service conduit to pathway Journeyman 16 105.00 1,680.00 Backhoe 8 175.00 1,400.00 5. Excavate existing handhold on pathway and remove service conduit from ground box and reinstall ground box with existing conduits with wiring Journeyman 16 105.00 1,680.00 Backhoe 8 175.00 1,400.00 6. Reroute service conduits around ground box Journeyman 16 105.00 1,680.00 Backhoe 4 175.00 700.00 Material - 50 ft. 2" Sch 40 PVC 50 3.36 168.00 $15,498.00 CO-6 Form Approved by Town Attorney – 05/15/2024 Attachment D BAKER CONCRETE SOLUTIONS 5660 Iris Pkwy Frederick, CO 80504 720-978-4904 Project Name :East Nottingham Park 10/9/2025 Project Address :1st Lake St. Avon, CO 2 Company Name :Baker Builders GC Directive ATTN. :Terry Been 0 Days Email Address :tbeen@bakerbuildersco.com 25-5133 SWD : Change Order Description: QTY UNIT RATE TOTAL 1 12 HR 58.45$ 701.40$ 2 3 4 5 6 7 701.40$ QTY UNIT PRICE TOTAL 1 2 YD 195.00$ 390.00$ 3 1 LS 150.00$ 150.00$ 4 1 LS 200.00$ 200.00$ 5 6 7 740.00$ QTY UNIT PRICE TOTAL 2 3 4 5 6 7 -$ 216.21$ 1,657.61$ Approved by :Baker Concrete Solutions :Johnatan Rodriguez Date:Date :10/9/2025 GRAND TOTAL Notwithstanding any provision to the contrary, by signing this Change Request, Owner represents and agrees that: (1) Owner approves the pricing set forth herein; (2) this Change Request shall automatically become part of the Contract Documents; (3) Baker and/or its subcontractors and/or suppliers are directed to proceed with the changed and/or extra work defined herein and the the supporting documentation; (4) Owner is obligated to pay for such work in accordance with the Contract Documents; and (5) Contractor is not responsible for any design errors or omissions resulting from such change. Other Expenses Total OVERHEAD AND PROFIT 15% Over Head/Profit Total Description Materials Total OTHER EXPENSES MATERIALS Material Description Concrete Formwork Rebar Labor Total East Park Seatwall foundation modification Labor Total LABOR DESCRIPTION 3 Guys 4 Hours , Form+Rebar , Place + Finish , Strip Forms Initiating Document : Schedule Impact : BCS Project # Change Order DATE : CO# 1 Silverback Excavation 5660 Iris Pkwy Frederick, CO 80504 720.552.5254 Page 1 of 1 Change Order Request #12 Project Name: East Nottingham Park Date: 10/7/2025 Project #: 25-8014 COR# 12 Description: Seat Wall – Reverse Footer Addition SCOPE ADDITIONS: See attached work order #7 from the Silverback Excavation Field ticket. The total cost to provide the Scope of Work described (see ATTACHMENT for breakdown): $1,455 SILVERBACK EXCAVATION BAKER CONSTRUCTORS Signature Signature Michelle Sheets Print Name _______ Assistant PM DATE Title DATE Notwithstanding any provision to the contrary, by signing this Change Request, Owner represents and agrees that: (1) Owner approves the pricing set forth herein; (2) this Change Request shall automatically become part of the Contract Documents; (3) Baker and/or its subcontractors and/or suppliers are directed to proceed with the changed and/or extra work defined herein and the supporting documentation; (4) Owner is obligated to pay for such work in accordance with the Contract Documents; and (5) Contractor is not responsible for any design errors or omissions resulting from such change. Description of Work: SILVERBACK EXCAVATION FIELD WORK ORDER TICKET Job Name: Date: Job #: Customer Name: - EQUIPMENT Description of Work Hours LDS/TNS/CY TOTAL MATERIALS USED Quantity Description TOTAL Silverback: Customer: Name: Name: Signature Signature 20251010_CO6_Paver Electrical Seatwall Final Audit Report 2025-10-19 Created:2025-10-10 By:Nicole Mosby (nmosby@avon.org) Status:Signed Transaction ID:CBJCHBCAABAABfykesHbRirsdOuazJCJgqXvu0dnzxcU "20251010_CO6_Paver Electrical Seatwall" History Document created by Nicole Mosby (nmosby@avon.org) 2025-10-10 - 5:43:44 PM GMT Document emailed to Nicole Mosby (nmosby@avon.org) for signature 2025-10-10 - 5:44:44 PM GMT Document e-signed by Nicole Mosby (nmosby@avon.org) Signature Date: 2025-10-10 - 5:44:58 PM GMT - Time Source: server Document emailed to tbeen@bakerbuildersco.com for signature 2025-10-10 - 5:45:01 PM GMT Email viewed by tbeen@bakerbuildersco.com 2025-10-10 - 5:54:01 PM GMT New document URL requested by tbeen@bakerbuildersco.com 2025-10-17 - 7:41:06 PM GMT Email viewed by tbeen@bakerbuildersco.com 2025-10-17 - 7:42:12 PM GMT Signer tbeen@bakerbuildersco.com entered name at signing as Terry W Been 2025-10-17 - 7:44:16 PM GMT Document e-signed by Terry W Been (tbeen@bakerbuildersco.com) Signature Date: 2025-10-17 - 7:44:18 PM GMT - Time Source: server Document emailed to Eva Wilson (ewilson@avon.org) for signature 2025-10-17 - 7:44:21 PM GMT Email viewed by Eva Wilson (ewilson@avon.org) 2025-10-19 - 10:49:58 PM GMT Document e-signed by Eva Wilson (ewilson@avon.org) Signature Date: 2025-10-19 - 10:50:50 PM GMT - Time Source: server Agreement completed. 2025-10-19 - 10:50:50 PM GMT