2024 Street Improvements – Swift Gulch Road Asphalt Overlay Project: Construction Change Order 3 CO-1 CHANGE ORDER Order No.:___3_________________ Date: ___ Oct 31, 2024______ Agreement Date: __ February 26, 2024__ NAME OF PROJECT: 2024 Street Improvements – Swift Gulch Road Asphalt Overlay OWNER: Town of Avon, Colorado CONTRACTOR: __GM Asphalt Repair LLC ________________________________ The following changes are hereby made to the CONTRACT DOCUMENTS: Justification: Driveway into Lot 5 Recycling Center is in poor condition and needs to be replaced. Eagle County and the Town of Avon are partnering 50/50 for all improvements. See Attached Proposal. Change to CONTRACT PRICE: $29,908 Original CONTRACT PRICE: $616,810.57 Current CONTRACT PRICE adjusted by previous CHANGE ORDERS $925,497.57. The CONTRACT PRICE due to this CHANGE ORDER will be increased by $29,908. The new CONTRACT PRICE including this CHANGE ORDER will be $55,405.57. Change to CONTRACT TIME: The CONTRACT TIME will be increased by __15__ calendar days. The date for completion of all work will be ___Nov 30, 2024____________________. APPROVALS REQUIRED: Approved by Engineer: Accepted by Contractor: Accepted and Approved by Owner: ______ Federal Agency Approval (where applicable): Not Applicable __________________ 1 $ ' . * ) — / B @ v A ? A C A @ w C E ˜10/31/2024 Martin Mendez (Nov 4, 2024 10:56 MST) Martin Mendez 11/04/2024 ri ei' (Nov 4, 2024 11:12 MST) +riF .eiO 11/04/2024 Attn- German & Martin Date- 10-9-24 SERVICE PROVIDER CUSTOMER GM ASPHALT REPAIR P.O. Box 3132 Eagle, CO 81631 Phone: (970) 343-2010 gmasphaltrepair@gmail.com Town of avon Lot 5 Project Description This quote only reflects an estimate of conventional paving job at lot 5 avon Note: 1- Gm asphalt is responsible for initial rough grade and sub-grade of desire pave area. 2- Excluded permits, traffic control, landscaping, plaiting, irrigation repair. 3- Owner is responsible for ensuring permits, layout and elevations conform to specifications and building codes 4- Proposal is based in current monthly fuel & material cost. In the event of price increases, we reserve the right to recover these costs. 5- Concealed conditions such as shallow utilities, boulders, sprinkler lines, stabilization of poor or soft subgrade is not included. 6- Any other work other than described above will be met with a change order and approved by owner/ contractor. Thank you for giving GM Asphalt repair the opportunity to bid your job ITEM # DESCRIPTION PRICE AMOUNT 1 HMA removal, prep, & new HMA for the west driveway (Approximately 14' × 74')
 $29,008.00 Two Sleeves for bollards $900.00 SUBTOTAL $ TOTAL $29,908.00 Payment to be made in full in TEN DAYS OF COMPLETION OF WORK UNLESS OTHER WISE STATED. GM requires 50% Deposit for material expenses before starting the project. Acceptance of proposal: The above prices, specifications and conditions are satisfactory and are hereby accepted. You are authorized to do the work as specified. Payment will be made as outlined above. Any payment not made on due date stated above will bear interest at the rate of 18% per year from the date the payment is actually received. If GM Asphalt Repair LLC has to commence legal proceedings to collect any or all of the amount due it, owner agrees to pay the reasonable attorney’s fees and any other expenses of GMAR LLC incurred in such proceeding. Name: _________________________ Signature: ______________________ Date of Acceptance: ______________ 20241031 - Change Order 03 - Lot 5 Recycling additional asphalt repair $29,908 Final Audit Report 2024-11-04 Created:2024-11-01 By:Eva Wilson (ewilson@avon.org) Status:Signed Transaction ID:CBJCHBCAABAAguFYdRuvsVBs2I0bWqNKV0hBlXeJ0OYQ "20241031 - Change Order 03 - Lot 5 Recycling additional asph alt repair $29,908" History Document created by Eva Wilson (ewilson@avon.org) 2024-11-01 - 3:45:24 AM GMT Document emailed to Eva Wilson (ewilson@avon.org) for signature 2024-11-01 - 3:46:41 AM GMT Document e-signed by Eva Wilson (ewilson@avon.org) Signature Date: 2024-11-01 - 3:46:50 AM GMT - Time Source: server Document emailed to gmasphaltrepair@gmail.com for signature 2024-11-01 - 3:46:51 AM GMT Email viewed by gmasphaltrepair@gmail.com 2024-11-04 - 5:55:42 PM GMT Signer gmasphaltrepair@gmail.com entered name at signing as Martin Mendez 2024-11-04 - 5:56:21 PM GMT Document e-signed by Martin Mendez (gmasphaltrepair@gmail.com) Signature Date: 2024-11-04 - 5:56:23 PM GMT - Time Source: server Document emailed to eheil@avon.org for signature 2024-11-04 - 5:56:24 PM GMT Email viewed by eheil@avon.org 2024-11-04 - 6:12:04 PM GMT Signer eheil@avon.org entered name at signing as Eric Heil 2024-11-04 - 6:12:43 PM GMT Document e-signed by Eric Heil (eheil@avon.org) Signature Date: 2024-11-04 - 6:12:45 PM GMT - Time Source: server Agreement completed. 2024-11-04 - 6:12:45 PM GMT