2024 Street Improvements – Swift Gulch Road Asphalt Overlay Project: Construction Change Order 1
CO-1
CHANGE ORDER
Order No.:___1_________________
Date: ___09 September 2024______
Agreement Date: __26 February 2024__
NAME OF PROJECT: 2024 Street Improvements – Swift Gulch Road Asphalt Overlay
OWNER: Town of Avon, Colorado
CONTRACTOR: __GM Asphalt Repair LLC ________________________________
The following changes are hereby made to the CONTRACT DOCUMENTS :
Line item #22: Additional 25 linear feet of curb & gutter for an additional cost of $1,375.00.
Line Item #18: Additional sawcut of 25 LF of asphalt paving to construct the additional
cub & gutter near the existing trailhead parking lot for an additional cost of $125.00.
We need to over-excavate and store in place approximately 230 cubic yards of
unsatisfactory soils for an additional cost of $76.00 per CY. ($17,480.00)
We need to import approximately 246 cubic yards of structural fill material to replace over-
excavated unsatisfactory soils for an additional cost of $47.00 per CY. ($16,215.00)
Justification:
Poor existing soil conditions beneath the proposed curb & gutter warranted over-excavation and
replacement with structural fill material. Furthermore, additional curb & gutter was warranted near
the trailhead parking lot to mitigate existing erosion issues.
Change to CONTRACT PRICE: $35,195.00
Original CONTRACT PRICE: $616,810.57
Current CONTRACT PRICE adjusted by previous CHANGE ORDERS $616,810.57.
The CONTRACT PRICE due to this CHANGE ORDER will be increased by $35,195.00.
The new CONTRACT PRICE including this CHANGE ORDER will be $652,005.57.
Change to CONTRACT TIME:
The CONTRACT TIME will be increased by __zero__ calendar days.
The date for completion of all work will be ___31 October 2024____________________.
APPROVALS REQUIRED:
Approved by Engineer:
,AGD G.:4җ1 +шѶспсурхѷпч2Ҙ
Qicole Posby
CO-2
Accepted by Contractor:
Accepted and Approved by Owner: ______
Federal Agency Approval (where applicable): Not Applicable __________________
9JLAF F Rҗ1 +шѶспсурхѷфц2Ҙ
#JA& ADҗ1 +рчѶспсупшѷфш2Ҙ
Hric .eil
CO 001 Swift Gulch Road Asphalt Overlay
Final Audit Report 2024-09-18
Created:2024-09-09
By:Nicole Mosby (nmosby@avon.org)
Status:Signed
Transaction ID:CBJCHBCAABAAvtX01hUT--PnQOSBLTq7PPkgFkSxJRJU
"CO 001 Swift Gulch Road Asphalt Overlay" History
Document created by Nicole Mosby (nmosby@avon.org)
2024-09-09 - 10:02:51 PM GMT
Document emailed to Nicole Mosby (nmosby@avon.org) for signature
2024-09-09 - 10:03:58 PM GMT
Document e-signed by Nicole Mosby (nmosby@avon.org)
Signature Date: 2024-09-09 - 10:08:04 PM GMT - Time Source: server
Document emailed to gmasphaltrepair@gmail.com for signature
2024-09-09 - 10:08:04 PM GMT
Document shared with LUlasich@avon.org by Nicole Mosby (nmosby@avon.org)
2024-09-09 - 10:11:45 PM GMT
Email viewed by gmasphaltrepair@gmail.com
2024-09-09 - 10:55:56 PM GMT
Signer gmasphaltrepair@gmail.com entered name at signing as Martin Mendez
2024-09-09 - 10:57:20 PM GMT
Document e-signed by Martin Mendez (gmasphaltrepair@gmail.com)
Signature Date: 2024-09-09 - 10:57:22 PM GMT - Time Source: server
Document emailed to eheil@avon.org for signature
2024-09-09 - 10:57:23 PM GMT
Email viewed by eheil@avon.org
2024-09-10 - 1:54:11 PM GMT
New document URL requested by eheil@avon.org
2024-09-18 - 3:56:33 PM GMT
Email viewed by eheil@avon.org
2024-09-18 - 3:59:22 PM GMT
Signer eheil@avon.org entered name at signing as Eric Heil
2024-09-18 - 3:59:46 PM GMT
Document e-signed by Eric Heil (eheil@avon.org)
Signature Date: 2024-09-18 - 3:59:48 PM GMT - Time Source: server
Agreement completed.