June Creek Emergency Access Improvements Project: Construction Change Order 2
CO-1
CHANGE ORDER
Order No.:_2____________________
Date: __07 June 2024_____________
Agreement Date: __01 May 2024____
NAME OF PROJECT: June Creek Emergency Access Improvements Project
OWNER: Town of Avon, Colorado
CONTRACTOR: _RPM Excavating & Pumping LLC__________________________________
The following changes are hereby made to the CONTRACT DOCUMENTS:
Over-excavation of unsatisfactory soils beneath the proposed retaining wall and replacement with
aggregate base course to the satisfaction of the geotechnical engineer.
Justification: Existing soils are unsatisfactory for supporting the proposed retaining wall, as
determined by the project’s geotechnical engineer.
Change to CONTRACT PRICE: $_735.87_________________
Original CONTRACT PRICE: $_285,901.84_____________
Current CONTRACT PRICE adjusted by previous CHANGE ORDER
__$290,938.69___________
The CONTRACT PRICE due to this CHANGE ORDER will be increased by
$_735.87____________.
The new CONTRACT PRICE including this CHANGE ORDER will be
$_291,674.56________.
Change to CONTRACT TIME:
The CONTRACT TIME will be increased by ____0____ calendar days.
The date for completion of all work will be _on or before 03 September 2024_________.
APPROVALS REQUIRED:
Approved by Engineer:
Accepted by Contractor:
Accepted and Approved by Owner: ______
Federal Agency Approval (where applicable): Not Applicable _________________
DocuSign Envelope ID: CD76A8BA-CB11-4CEB-A6F1-2F09E432CF53
1
Nicole Mosby
From:Justin J. Yarnell <justin@theyarnells.com>
Sent:Monday, June 3, 2024 7:29 PM
To:Nicole Mosby
Subject:June Creek Emergency Egress: COR for Wall
Nicole,
Below are the numbers for RPM to complete the over-excavation and gravel backfill
beneath the wall, as per the request of CMT Technical Services. Can we approve this
$735.87?
*Please note I will be on personal vacation from June 25 through July 17 -- returning to work on July 18.
Let's coordinate project schedules to ensure no deliverables are needed during this period. Thank you!*
Best,
Justin Yarnell, PE (CO)
Justin@TheYarnells.com
Office: (970) 323-7008
EAGLE RIVER VALLEY:
P.O. Box 3901
Eagle, Colorado 81631-3901
ROARING FORK RIVER VALLEY:
229 Midland Ave.
Basalt, Colorado 81621
BY RECEIVING THIS ELECTRONIC INFORMATION, including all attachments, the receiver agrees that this data may not be modified or
transferred to any other party without the prior written consent of Justin Yarnell, that this electronic information may not necessarily
represent the information shown on the recorded or approved final developments and/or documents, and that the receiver is responsible for
verifying the information contained within the electronic data against the recorded or approved final documents. This privileged and
confidential information is intended only for the use of the addressee(s) named above. Anyone who receives this communication in error
should notify us immediately by reply e-mail.
---------- Forwarded message ---------
From: Marie-Christine Carel <mccarel@rpmconstruction.co>
Date: Mon, Jun 3, 2024 at 4:24 PM
Subject: RE: June Creek Emergency Egress Pay App. #2 Questions
To: Justin J. Yarnell <justin@theyarnells.com>
Cc: Roby Forsyth <rforsyth@rpmconstruction.co>
Justin,
DocuSign Envelope ID: CD76A8BA-CB11-4CEB-A6F1-2F09E432CF53
2
Here is the cost for the additional excavation associated with the retaining wall subgrade; we would like it
approved asap as we are starting to receive the blocks on Thursday and would like to fill the back of the wall prior.
2hrs of mini excavator : $250
1hr of compactor : $110
10 cy 3” fill: $370.87
Total: $735.87
Marie-Christine