June Creek Emergency Access Improvements Project: Construction Change Order 1 CO-1 CHANGE ORDER Order No.:_1____________________ Date: __06 June 2024_____________ Agreement Date: __01 May 2024____ NAME OF PROJECT: June Creek Emergency Access Improvements Project OWNER: Town of Avon, Colorado CONTRACTOR: _RPM Excavating & Pumping LLC__________________________________ The following changes are hereby made to the CONTRACT DOCUMENTS: The addition of geotechnical testing services for the existing, on-site soil materials. The CO amount reflects the cost from CMT plus a 5% markup. Justification: The previous town engineer opted to delay the geotechnical investigation to the start of construction instead of the start of design. This was overlooked during the bidding and contracting process. Change to CONTRACT PRICE: $_5,036.85_______________ Original CONTRACT PRICE: $_285,901.84_____________ Current CONTRACT PRICE adjusted by previous CHANGE ORDER $__285,901.84___________ The CONTRACT PRICE due to this CHANGE ORDER will be increased by $_5,036.85____ The new CONTRACT PRICE including this CHANGE ORDER will be $_290,938.69_____ Change to CONTRACT TIME: The CONTRACT TIME will be increased by ____0____ calendar days. The date for completion of all work will be _on or before 03 September 2024_________. APPROVALS REQUIRED: Approved by Engineer: Accepted by Contractor: Accepted and Approved by Owner: ______ Federal Agency Approval (where applicable): Not Applicable _________________ DocuSign Envelope ID: 00841E69-2CC4-4AF8-9F69-7A566547069F DocuSign Envelope ID: 00841E69-2CC4-4AF8-9F69-7A566547069F