2024 Street Improvements – Upper Buck Creek Road Asphalt Overlay Project: Construction Change Order 3 CO-1 CHANGE ORDER Order No.:___3__________________ Date: ___26 July 2024____________ Agreement Date: __26 February 2024__ NAME OF PROJECT: 2024 Street Improvements – Upper Buck Creek Road Asphalt Overlay OWNER: Town of Avon, Colorado CONTRACTOR: __Grand River Construction Company________________________________ The following changes are hereby made to the CONTRACT DOCUMENTS: • Line item #10: Additional 432.5 feet of guardrail was adjusted (due to an error in the bid tab quantity) for an additional cost of $1,773.25. • Line item 11: There was a reduction of 124.5 feet of guardrail that was removed and replaced for a savings of $8,092.50. • We replaced 58 wood blocks within the project limits for an additional cost of $4,930.00. • We reused 50 existing posts when the rails, hardware, and blocks were all replaced. This yielded a credit of $4,250.00. Justification: The field conditions warranted some adjustments to the project scope to better fit the town’s investment. Change to CONTRACT PRICE: $5,639.25 Original CONTRACT PRICE: $649,465.76_____________ Current CONTRACT PRICE adjusted by previous CHANGE ORDERS $576,280.86. The CONTRACT PRICE due to this CHANGE ORDER will be decreased by $5,639.25. The new CONTRACT PRICE including this CHANGE ORDER will be $570,641.61. Change to CONTRACT TIME: The CONTRACT TIME will be increased by __zero___ calendar days. The date for completion of all work will be ___01 July 2024____________________. APPROVALS REQUIRED: Approved by Engineer: Accepted by Contractor: Docusign Envelope ID: 749A7DBD-0DE1-4CF9-8408-4C15C82F5824 CO-2 Accepted and Approved by Owner: ______ Federal Agency Approval (where applicable): Not Applicable __________________ Docusign Envelope ID: 749A7DBD-0DE1-4CF9-8408-4C15C82F5824