2024 Street Improvements – Upper Buck Creek Road Asphalt Overlay Project: Construction Change Order 1
CO-1
CHANGE ORDER
Order No.:___1__________________
Date: ___05 June 2024____________
Agreement Date: __26 February 2024__
NAME OF PROJECT: 2024 Street Improvements – Upper Buck Creek Road Asphalt Overlay
OWNER: Town of Avon, Colorado
CONTRACTOR: __Grand River Construction Company________________________________
The following changes are hereby made to the CONTRACT DOCUMENTS:
Removal of unsatisfactory subgrade material near station 61+00. Then placement of geogrid, new
subgrade material, and 6-inch asphalt pavement.
Justification:
The existing subgrade was in exceptionally poor condition. Placement of new asphalt on this
material would have resulted in near immediate failure.
Change to CONTRACT PRICE: $_3,533.00_______________
Original CONTRACT PRICE: $_649,465.76_____________
Current CONTRACT PRICE adjusted by previous CHANGE ORDER
$__649,465.76__________
The CONTRACT PRICE due to this CHANGE ORDER will be increased by
$__3,537.00____________.
The new CONTRACT PRICE including this CHANGE ORDER will be
$__653,002.76__________.
Change to CONTRACT TIME:
The CONTRACT TIME will be increased by __one___ calendar days.
The date for completion of all work will be ___01 July 2024____________________.
APPROVALS REQUIRED:
Approved by Engineer:
Accepted by Contractor:
Accepted and Approved by Owner: ______
Federal Agency Approval (where applicable): Not Applicable __________________
DocuSign Envelope ID: 9C6C108E-F63F-440D-95D2-8384F8931B8D
DocuSign Envelope ID: 9C6C108E-F63F-440D-95D2-8384F8931B8D