Notthingham Rd Basin 4 Sediment Pond and Channel Improvements Project: Construction Notice of Final SettlementNOTICE OF FINAL SETTLEMENT
10/29/2024
In accordance with the notice provisions contained in 38-26-107 C.R.S. I 973, the Town
of Avon, Colorado, has established November 11, 2024 as the date of final settlement
with H&L Concrete, Inc. dba Naranjo Civil Constructors, Inc, a Colorado
contractor, for the NOTTINGHAM RD BASIN 4 SEDIMENT POND AND
CHANNEL IMPROVEMENTS Project, situated in the Town of Avon, Eagle
County, State of Colorado. The Project consisted of clearing and grubbing, erosion
control, channel and sediment pond grading, excess material haul-off, Flexamat
installation, concrete weir installation, soil preparation, seeding, and asphalt driveway
replacement.
Claims containing a verified statement of the amounts due and unpaid must be in the
form of a written affidavit and must be received by the Town Engineer, of the Town of
Avon at Town Hall, 100 Mikaela Way, P.O. Box 975, Avon, Colorado 81620, on or before
5:00 PM of the final settlement date above.