PZC Packet 030486STAFF REPORT TO PLANNING & ZONING COMMISSION - 3/4/86
Lots 26-28, Block 1, Benchmark at Beaver Creek
Mountain Center - Informal Discussion
Continued from 2/18/86 Regular Meeting
INTRODUCTION:
This will be an informal presentation for the purpose of receiving guidance
from the Commission prior to development of final plans. The following items
are brought to the Commission's attention to possibly assist in providing
this guidance:
1. Proposed plan indicates 103 parking spaces including three stacked
spaces which are not normally allowed in parking requirement computations.
Minimum parking requirements for the 82,380 square feet floor area is
1/800 square feet or 103 spaces. Potential uses such as automotive
or other vehicular repair, retail sales or general offices could
increase parking requirements even more;
2. Landscaping and snow storage areas appear to be very limited;
3. Driveway at westerly end of project is located in drainage easement.
Debris flow problems have been experienced in this easement within
past years. Provisions for water and debris flow in this area are
critical;
4. Pole mounted lights along southerly edge of project could provide
light for both project and street;
5. Grading along northerly property line as shown at 112:1 slope which
will require careful consideration for revegetation;
6. Plans do not indicate any provision for trash storage;
7. Specific comments regarding building design would probably be most
beneficial to applicant.
Respectfully
Ray Ylright
Engineering
RW/mnl
Submitted,
Technician
STAFF REPORT TO PLANNING & ZONING COMMISSION - 3/4/86
Lot 3, Sunroad Subdivision
First Bank of Avon
Site Plan Design Review
INTRODUCTION:
At the February 16, 1986 meeting, the Commission gave final approval to the
building design, materials, and colors for the First Bank. Final approval was
also granted for the proposed signage for the project, subject to Staff review
of the allowable square footage. The site plan was given preliminary approval
subject to the following five Staff recommendations:
1. Future access at northeasterly corner of property be deleted or
noted as "Exit Only";
2. Temporary access from Beaver Creek Boulevard be subject to execution
of agreement stipulating conditions for removal of entrance;
3. Suggested parking lot lighting be HPS pole mounted, maximum height
of 25 feet;
4. Sidewalk materials be designated;
5. Site grading and drainage plan be revised to conform with revised
site development plan.
Concern was also expressed about landscaping on the west side of the _project,
and traffic circulation.
The applicant has submitted a revised site plan addressing some of the Commission's
concerns. The future access at the northeasterly corner of the project is now
shown as "Exit Only", parking lot lighting is shown as pole mounted, high pressure
sodium lights, with bollard lighting at the entrances to the site and along
walkways. A seven foot wide landscaping strip has been added between the ATM
lane and the parking spaces to the west.
STAFF COMMENTS:
Although the revised site plan shows an area for landscaping just west of the
ATM lane, no revised landscaping plan has been submitted showing plant materials,
sizes or quantities proposed for this area.
The radius of the circular drive for the ATM lane has been increased slightly,
but traffic circulation in this area remains the same as in the previous sub-
mittal.
Staff was directed to check the allowable square footage for the proposed signs.
If the signs are considered to be part of an overall sign program for the project,
the proposed 96 square feet is the maximum allowed under the current sign code
without a variance procedure.
Staff Report to Planning & Zoning Commission - 3/4/86
Lot 3, Sunroad Subdivision
First Bank of Avon
Site Plan Design Review
Page 2 of 3
STAFF RECOMMENDATIONS:
If final approval is granted, Staff recommends that such approval be subject to
the following conditions:
1. That the temporary access from Beaver Creek Boulevard be subject to the
execution of an agreement, satisfactory to the Town Attorney, Stipulating
the conditions for the removal of the entrance, prior to issuance of a
building permit;
2. That a revised landscaping plan be submitted for Commission approval;
3. That the material for the sidewalk along Beaver Creek Boulevard be
concrete;
4. That the site grading and drainage plan be revised to conform with
revised site plan and be submitted for Staff approval.
RECOMMENDED ACTIONS:
1. Introduce project;
2. Presentation by applicant;
3. Commission review of submitted materials;
4. Action on application.
Respectfully Submitted,
Ray W6�5 yht
Engineering Technician
Staff Report to Planning & Zoning Commission - 3/4/86
Lot 3, Sunroad Subdivision
First Bank of Avon
Site Plan Design Review
Page 3 of 3
Planning and Zoning Action:
Approved as Submitted ( ) Approved with Recommended Conditions (HCl
Approved with Modified Conditions ( ) Continued ( ) Denied ( ) Withdrawn ( )
Date Patri ci a Cuny, Secretary
/I _. . 7e- ,
RW/mml
STAFF REP' TO PLANNING & ZONING COMMISSION - 3/4/86
Lot 38, Block 3, Wildridge Subdivision
Ricks Duplex
Preliminary Design Review
INTRODUCTION:
Roy Ricks has submitted an application for design review of a duplex residence
to be located on Lot 38, Block 3, Wildridge Subdivision. The proposed building
is approximately 5,900 square feet. Building materials include R -wall exterior
insulation system with a stucco -like finish proposed to be light sage in color.
Roof material is sawn cedar shingles and fascia will be rough sawn cedar.
Plans submitted include a site plan, floor plans, building elevations, and a
landscaping plan.
STAFF COMMENTS:
The site plan is fairly complete but is lacking some dimensions. No building
ties or dimensions are shown, and the parking area should be dimensione as
well. Parking for 8 cars is provided on-site. Four spaces are outside a
each unit has its own 2 car garage. The site plan shows some minor grading
for drainage but does not show a culvert at the driveway entrance.
The landscaping plan shows a variety of plant materials, but no sizes or
quantities are shown. No reference is made to any irrigation system on the plan.
STAFF RECOMMENDATIONS:
If preliminary approval is granted on this project, Staff recommends that the
following items be addressed prior to final approval:
1. Site plan be revised to show building ties and dimensions, parking and
drive dimensions, and culvert for drainage in the street right-of-way;
2. Landscaping plan be revised to show sizes and quantities of proposed
plant materials- and reference be made to type of irrigation sy!�em to
be used.
RECOMMENDED ACTIONS:
1. Introduce project;
2. Presentation by applicant;
3. Commission review of submitted material;
4. Action on application.
Reectfull_v Submitted,
a"
Rayke
ht
Eng g n
ri�Te hnicia
Staff Report to Planning and Zoning Commission - 3/4/86
Lot 38, Block 3, Wildridge Subdivision
Ricks Duplex
Preliminary Design Review
Page 2 of 2
Planning and Zoning Action:
Approved as Submitted ( ) Approved with Recommended Conditions X)
Approved with Modified Conditions ( ) Continued ( ) Denied ( ) Withdrawn
nate ��5��.�C Patricia Cuny, Secretary /�rQJ
Pd!nnni
STAFF REPORT TO PLANNING & ZONING COMMISSION - 3/4/86
Lot 7. Block 1, Wildridge Subdivision
Suncrest Phase II
2 Triplex Units
INTRODUCTION:
At the August 30, 1984 meeting of the Commission, approval was given to build
2 triplex buildings consisting of 3 levels per building. Each of the 6 units
was to have approximately 2,200 square feet of living area and a single car
garage.
The design review file contains a color rendering of the approved building
elevations. Colors selected and approved for the buildings were a blue -gray
for the building's siding and trim with blue accent for the railings.
On July 29, 1985 the building permit was issued to Steve Wydeveld for Suncrest
Phase II. The plans that were submitted for the building permit review revealed
the same building elevations that were approved at the August 30, 1984 Commission
meeting.
The building was built during the last 5 months of 1985 with completion of the
structure on December 23, 1985. A Temporary Certificate of Occupancy was issued
for Pnase II on December 23, 1985.
During the first week of February, 1986 Ray Wright brought to my attention the
fact that the building (as-builts) did not comply with the approved plans of
the Commission. Further investigation revealed t�-2e areas that did not comply
with the approved design review plans:
1. Roof line and roof overhangs;
2. Windows and doors at ground level and windows on 3rd level;
3. Color of building and color and style of railings.
The builder was notified of these discrepancies and a meeting arrangement
finally made for February 25, 1986. The builder was asked to bring to that
meeting possible solutions to resolve the problems. Staff asked for and
received a letter from the builder as well as photographs of the existing
building for the purpose of comparison and to be presented for consideration
by the Commission.
. N
Staff Report to Planning & Zoning Commission - 3/4/36
Lot 7, Block 1, Wildridge Subdivision
Suncrest Phase II
2 Triplex Units
Page 2 of 3
STAFF COMMENTS:
To produce the approved building at this stage would require the builder to
do the following:
1. Remove roof;
2. Reframe exterior walls to accept approved windows and doors;
3. Reframe roof with overhangs;
4. Reroof;
5. Remove and install approved railings;
6. Paint to approved colors.
Staff offers to the Commission, for consideration, the following questions:
1. The definition of the existing building is less pronounced as compared
with the approved plans. By adding overhangs without changing the roof
lines, would the building take on a tacked -on appearance, thus diminishing
the original design?
2. The color of the existing building blends with the surrounding buildings,
and by going to the original color scheme, would the building stand out
and appear out of place?
3. Does the option exist to have the builder build this phase as to the
approved plans?
4. If this existing building is approved as a change to the .asign review,
then what happens to color and design with regard to the second building?
STAFF RECOMMENDATIONS:
1. Staff recommends that the existing building be approved as a modification
to the approved design review plans. Color blends well and by adding
overhangs, the design would be diminished.
2. In regard to the second building, Staff recommends the design of this
building be approved with the original design guidelines in mind, except
the railings to be the same as existing building if that building is
allowed to remain. Colors of this building should be the same as the
first phase.
i
STAFF REPORT TO PLANNING & ZONING COMMISSION - 3/4/86
Lot 7, Block 1, Wildridge Subdivision
Suncrest Townhomes, Phase II, Unit B
Exterior Stairway Design Review
Continued from 2/18/86 Regular Meeting
INTRODUCTION:
The owner of Unit B, Dr. George H. Schmidt, D.D.S. has applied for design review
approval for an outside stairway. The proposed stairway would provide direct
access from the outside parking area to the main living area of the unit.
The issues involved with this application include both design review and zoning.
The design review issues are relatively simple. The design is for a stairway
to be constructed from ground level to a second level balcony. The stairway
extends perpendicular to the front of the building and is to be constructed from
matching materials. The design issues include:
z) The suitability of the imprcvement, including materials of which it is
to be constructed and the site upon which it is to be located;
b) The nature of adjacent and neighboring improvements;
c) The quality of materials to be utilized in any proposed improvement;
d) The visual appearance of any proposed improvement as viewed from any
adjacent or neighboring property;
e) The objective that no improvement will be so similar or dissimilar
to others in the vicinity that values, monetary or aesthetic, will be
impaired.
The zoning issues are much more complex. The installation of an outside stairway
appears to create, or at least creates the potential for, an additional dwelling
unit or lock -off unit. The creation of either an additional dwelling unit or
a lock -off unit would require additional Development Rights and parking spaces,
neither of which have been provided for in the application.
STAFF COMMENTS:
Dr. Schmidt submitted the attached letter dated February 26, 1986 in which he
states the stove and microwave will be removed from the lower level along with
the door between the first and second levels. These alterations would technically
meet the requirements for eliminating the additional dwelling unit or lock -off
unit as the case may be. However, future owners of the unit may not be as
conscientious as Dr. Schmidt and the cooking facilities and door could be
reinstalled at any time. These changes are entirely within the unit and cannot
be monitored since the work required to reinstall the cooking facilities and
doors would not require a building permit.
Statf Report to P':anning & Zoning Commission - 3/4/86
Lot 7, Block 1, Wildridge Subdivision
Suncrest Townhomes, Phase II, Unit B
Exterior Stairway Design Review
Continued from 2/18/86 Regular Meeting
Page 2 of 2
STAFF RECOMMENDATIONS:
Staff recommends the application for design review approval for an outside
stairway for Unit B, Suncrest Townhomes, Phase II be denied based upon:
1. Potential zoning conflicts;
2. The design of the proposed improvements is incompatible with the overall
building design resulting in an unacceptable level of dissimilarity between
adjoining units.
RECOMMENDED ACTIONS:
1. Introduce application;
2. Presentation by applicant;
3. Consideration and action 'y Commission.
Respectfully Submitted,
- ��
Norm Wood,
Director of Engineering and
Community Development
Planning and Zoning Action:
Approved as Submitted ( ) Approved with Recommended Conditions ( )
Approved with Modified Conditions ( ) Continued ( ) Denied (� Withdrawn ( )
Date 3/Tlw Patricia Cuny, Secretary��C�;o�J
NW/mml