PZC Minutes 121493SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Members Present: John Perkins, Sue Railton,
Buz Reynolds, Patti Dixon,
Rhoda Schneiderman,
Henry Vest
StaffPresent: Steve Amsbaugh, Director
of Community Development;
Mary Holden, Planner
The meeting was called to order at 3:15 PM with all members present except Henry Vest
and Jack Hunn. Henry Vest arrived at 4:30 PM.
Aquatic Center, Conceptual Design Review
Steve Amsbaugh stated that the design team for the Aquatic Center was present to
discuss, basically the site plan for the Aquatic Center, and they will also discuss the
components of the Library that are general in nature. They will also discuss the
conceptual design to find out if the Commission has any comments or concerns about the
direction they are heading. They will be going through the design review process at a later
date. He stated that after the meeting, a joint meeting of the Commission and Town
Council is scheduled to review the comments and concerns.
W. Amsbaugh introduced Chris Carvelle, with C W Ventres, to make the presentation.
Mr. Carvelle introduced his team as, John Bebel, the contractor; Kelly Dunn, project
architect, Michael Hazard, associate architect, Paul Kuen, landscape architect, and Chris
Squadra, the Town of Avon's representative.
Mr. Carvelle stated that the single big move is the moving of Benchmark Road over to the
back portion of the sit%thus expanding the whole park, without having the divider with
through traffic. He described on the plans where Benchmark Road goes now. He pointed
out the tennis courts that will be relocated to the other end of the lake. He stated that one
of the things that they were not able to incorporate was the pond. One of the things they
are trying to do is maximize the open space, the amount of green space and the amount of
connection between the Library and the rec center with the park and form a gateway to
the park that extends your pedestrian Town Center Mall all the way through and into the
park. They were also able to preserve the volley ball courts and create a lot of pedestrian
P" 1
n
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Page 2
Aquatic Center, Conceptual Design Review. (cont)
connections throughout the whole area. He pointed out on the plans where the bus drop-
offs would be. This will allow being able to get to the whole complex from two ends of
the site, allowing through traffic to go through and not impact the pedestrian experience in
the two buildings, and not impact the connection coming through from the Town Center.
He stated that this is not a final design as far as detail. There will be a lot more definition
to entrances, etc. The development of their entry to the building will take on a lot more
character than it currently has. There is actually in plan, the wall of the building really cuts
back underneath the building and the large overhang for the aquatic center forms a nice
large sundeck patio that has some shade and some exposure to the southwest. The
building is also on a strong southwest axial entry and drop-off zone to the park in terms of
its sun exposure and views down to the lake. One thing that they have tried to avoid is
any north or east entry to the building itself. All of this was trying to get the library
included as a partner in this marriage of buildings that has a lot usage. What they are
trying to do is make this building a pavilion on the park. They are trying to break down
the scale of all the pieces and parts that are going to be in this building, so that there isn't
going to be any one massive expression of the building. The best view of this site is not
on the plans. The best view is from above at Beaver Creek. The fifth elevation of this
building is very critical. How this building looks is the evening, they have a lot of
mechanisms for daylight and lighting this building a: night, so this becomes a beacon. This
has the potential of becoming a new identity for Avon. This is a European style, indoor
leisure pool, that will be basically an indoor component that has cropped up here in
Colorado. It is not just a lap pool. There are phases also. This is the ultimate design that
the Commission is seeing tonight. They will be coming back in January with a model so
that the Commission can get a sense of the scale. The building has been pulled back, but
the road has been pulled back behind it, so this is basically doing two things, both
b-ildings become a marriage. It becomes one grouping with the library, acquatic center,
fire station and town hall.
Regarding the parking count, they felt that this building needed a minimum of 150 spaces,
collectively, not counting the specific spaces that are in front of town hall or the fire
station or the spaces next to the railroad tracks, they are now at 196, so they have
increased the count from where they were the last time. They have worked with Larry
Brooks and Bill James, and Inter -Mountain Engineering, who will be doing the
engineering for both teams on this project, in terms of the road relocation and both the rec
center and the library. Hopefully in April the construction for the relocation of
Benchmark Road and some of the relocation of the key utilities and drainage ditches will
begin. They are on a fast track mode of trying to get the road construction, at least under
way and bid out early spring.
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Page 3
Aquatic Center. Conceptual design Review, (cont)
Mr. Carvelle described the floor plan for the building. He stated that the main entrance to
the building is on the south and west access. The aquatic center is in the south west
corner of the site, to be able to get as much daylight and openness to the aquatic center as
possible, as well as the view of the park. There will be a soft curved metal roof to
minimize the massing of the building and also to get the snow off some very long spans
across there. It will have a lot of different features in it. When you walk in the door you
will be walking through an enlarged stone lodge like fireplace element that sets off the
main entry. They have yet to choose exactly what stone they will use. That kind of
material will occur in column details around the building. It will also clearly direct people
to the front door and it has an image of the mountain peaks in the surrounding valley. As
a part of that it turns into a large stone fireplace and then a lounge area which is off the
main gallery and looks straight out on to the aquatic facility. When you walk in the front
door you are in full view of the aquatic center when you walk into the gallery space. As
you walk in there will be control desk, which controls people going into the athletic
portions of the facility. You cannot get to any of the center without going past the control
desk. There will be one side that will be a community side that will have a separate
entrance. This will be a community center for meetings, seniors, etc. The control desk is
at the pivot of all the athletic spaces. The day care center, the aquatic center, and the
aerobic/weight area all are in Phase I of the plan. The conference center and gym are in
the future. There is a lot of thought in terms of controlling how you get into the facility,
in terms of supervision by the staff. One of the goals of the facility is to have a lean and
mean staff in terms of how this facility is used to keep down the operation costs of the
building. In conjunction with that, operational costs have a lot to do with how the
building is massed out, building form itself, how daylight is brought into this building and
how the breakdown and scale and massing came about. This is a massing of several
structures. In plan, they are trying to have every piece of the building have it's own
identity off one central access point. That is one of the big concerns with Town Council is
the scale. They are trying to bring daylight in a lot of different places. He described how
they are trying to clearly express the integrity of the space, which is the long span
structure, and in the mountains, the post and beam is something that is expressed in the
lodge vocabulary across Colorado. They have drawn their vocabulary on Beaver Creek,
and the Vail Valley and the peaks around the area. Also, there is a lot of glass there and
they are setting it way back because they don't want it to be a curtain wall building. It
wants to have a lot of shade and shadow and a lot of relief to it and a lot of setback
underneath the roof form which is curved. There will be a nice column and base detail out
front, with the glass behind it. They are trying to control heat gain and heat loss, but be
able to maintain maximum visibility and sun penetration to the space without the heat
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Page 4
Aquatics Center. Conceptual Design Review. (cont)
gain/heat loss characteristics. They are going to do a low "E" glass, which has a reflective
characteristic to it, but it will be on the second or third surface within the glass itself.
Carvelle stated that the snow will come off as it comes down. It will not build up on the roof. Also, the
walkway system is away from the building. Discussion followed on the possible stone to
be used. The amount of metal that will be showing was also discussed. Discussion
followed on the curved roofs and the three dimensional quality of the building. Rhoda
Schneiderman felt that it was kind of unbalanced. There is so much glass and so little of
the solid variety in the first Phase. There is a possiblilty that the other half will not get
built. The massing model will give them a better idea of how it will look without the
second Phase. Mr. Carvelle stated that they are just looking at the front of the building.
There is a lot of major masonry solid portions of the building. He stated that this will add
to the park, because right now there are a lot of big blank walls on most of the buildings
around the park. The other elevations were then discussed. Discussion followed on the
color of the roof. They are looking at it being sort of a peweter color, kind of neutral.
Discussion followed on the other colors. They will pick up the sky and water color and
then counterpoint that with a warm tone in the masonry. They want to carefully use the
stone and brick. The bricks will be in patterns. The possibility of using sandstone was
discussed. Sue Railton asked if they had thought about any other elements for the
entrance other than the glazing. She felt it looked like a department store. Rhoda
Schneiderman stated that when you use the post and beam concept in metal it is not the
same. It is not a mountain environment. What most people will see is an extremely
modem building. She stated that she kind of likes the building and it has potential, but she
is not sure it will fit well in the space they have to work with. She doesn't think that we
can build something so different that it will not blend. It should have some sort of
cohesion with the park, instead of having this big building that doesn't fit well in the
landscape. She asked if they had given any thought to putting a lap pool on the outside so
that parents and onlookers watching their kids from the lobby space can see their kids
playing instead of having to look across another pool. Mr. Caravelle stated that the
reason that this is down here is that this has a lot of vertical elements, big slides, structures
and bridges, and very httle activity as compared to having most of the people in this zone.
The layering of low intensity of the lounge space was a concern acoustically and
aesthetically. John Perkins asked if there was any possibility of breaking the massing over
the pool and the lazy river, to break up this very large mass. He thinks that they are going
to read two strong masses. It is a better building without the gym. He questions putting
the cars between the building and the park. He feels it is unfortunate that they cannot
park under the building. He is concerned with the people figuring out how to get to the
parking lot. He also had some concerns regarding some of the other elevations
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES.
December 14, 1993
Page 5
Aquatics Center. Conceptual Design Review. (cont)
He stated that he finds the site planning a bit awkward. Discussion followed on why the
site plan was done this way. Discussion followed on the lack of bus transportation and the
need for people to drive their car to where ever they are going.
Discussion followed on the roof lines. Discussion followed on the matter of identifying
the entrance to the parking lot. Discussion followed on the need for two entrances, one
for autos and one for pedestrians.
Steve Amsbaugh stated that it was time to meet with the Town Council. Buz Reynolds
stated that he has several things to bring up on this. The applicant will come back for
more conceptual review at the December 21st meeting.
The Seasons At Avon. Final Design Review of Modifications
Steve Amsbaugh stated that the owners and developers of The Seasons At Avon, formerly
known as the Peregrine Building and Grand on Avon, requested last week a special
Planning and Zoning meeting to review several items relating to design review approvals.
they already have final design approval for the building as it stands. They also received
various minor approvals in about 1990 that never really stuck with the approved project,
like a schematic for a porte cochere and other parking plan. Those they are revising and
will be presenting them tonight. Amsbaugh stated that he has listed in the Staff Report a
series of overall design approvals that they will seek over the next weeks. They will not
have them all tonight. He stated that they ought to discuss these items one at a time, that
way if the Commission is comfortable with one approval they can approve it and move
along and if they are uncomfortable with something else they can research that further.
That way the whole project is not stopped. They would like to get going on the Vail
Associates side of the business. It is a final design process and these are modification to
the approved plans. He asked the applicant to give a brief overview of where they are
heading with the building.
Steve Elken stated that he is the project director for the development side of the building.
He introduced Tom Gart, one of the owners of the building. Mr. Elken stated that the
Gart Company and theirselves are developing and selling off the condominiums. The first
floor is a joint venture development of the Gart Company and Vail Associates. Vail
Associates will occupy approximately 85 percent of the first floor. The existing, approved
plan shows approximately 58,000 square feet of net leasable, and the revised plan adds
about another 10,000 square feet in what is called the open mail between the south
building and the first floor of the high rise building. The proposal is to enclose the
10'
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Page 6
The Seasons At Avon, Final Design Review Modifications_ (cont)
"football" shaped area, or pedestrian mall area, to create additional office space, plus
common area space for the employees and residents. Buz Reynolds asked if this will
effect the parking. Steve Amsbaugh stated that there are 356 spaces available, 292
underground, 33 on-site surface and 31 at the project you just looked at. If an analysis is
done with their new square footage, they need 355 spaces, so they are one over. In terms
of codes they are alright. Rhoda Schneiderman asked where the 33 spaces are. Mark
Donaldson stated that it is on the south side. As you enter the one way drive from the east
there is diagonal parking on the left and right and as you head out there is the same thing.
The idea is that the first time user can get familiar with the site. The central theme of the
porte cochere is to allow the first time user to come into the central corridor and get
directions.
Steve Elken stated that the basic plan is to have about 60,000 square feet of office type
use, with Vail Associates and their entities and about 10,000 square feet of retail type
uses. They will begin in the near future marketing for the retail space. There are 103
condominium units. They have chosen to re -position the building as we!I as renaming it .
They felt that they want to play up the vitality of the four seasons in the valley, thus the
name The Seasons and the colors, as well as the four towers, will be treated as a different
season of the year and they will each display a different color of the year, all
complimentary to each other. John Perkins stated that it is a great scheme to break down
the massing of the building. On the south side of the building they are opening up half of
the balconies with open railings to open up from the inside of the building. Some one
sitting in their living room will now be able to see the golf course, etc. They are doing
certain upgrades. They have put brand new roofs on all the buildings. They have hired
Communication Arts out of Boulder, who are very people oriented on how to develop
themes, colors and finishes to make it user friendly and to make it an important component
of the community. Some of the aspects of Vail Associates will be their marketing, their
executive offices, their legal department, bookkeeping services, etc.
Tom Gart stated that the major change they are making is that they are closing the gap
between the front building and the back building and this will facilitate the traffic flow and
bring alive the mall the Town put in long ago. Mark Donaldson stated one last link
between the uses and the building, Vail Associates is managing the condominium sales and
will also manage the hotel operation that will help bring the commercial and the residential
together in an operation for years to come. Management is on-site.
Steve Amsbaugh stated he wanted to give an overview of all the elements of all the plans
that are going to be before the Commission and then discuss the ones that will be
a
a
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Page 7
The Seasons At Avon, final Design Review of Modifications. (cont)
presented tonight. With Mark and Communication Ars on board and the ideas that Steve
reflected in terms of the name and the theme of the building, some of that is reflected in
design solutions for the exterior of the building. Some of those that are identified in the
Staff Report are: the new color scheme, which will reflect the seasons, and this will be
discussed in detail; a modified architectural on the central towers; a revised detail along
that long front first level commercial roof facade; a revised Porte cochere on the south
entrance; a new enclosure for the "football' area between the main building and the south
commercial building; new chimney caps for the roof -top chimney clusters; revised
balcony rail details, which will be presented at a future meeting; new garage doors for the
two garage entrances will be at a future meeting; revised Master Sign Program will be at
a future meeting; and there are a seriesof miscellaneous stairs, windows and doorways
that will probably be addressed in a future meeting. That is the overview of all the things
that will be coming before you. The most important that will be presented tonight are
colors, the towers, some of the articulation along the commercial area and the enclosure of
the football area, and the pone cochere.
Amsbaugh stated that site plan modifications are normally discussed at final design review,
but at this time they are not proposing and site plan modifications. They will be coming
before the Commission in the future with landscape details along the porte cochere and
that existing wall. There probably will be some mall side improvements made in terms of
landscaping, in the future. There are six building modifications that are being presented at
this time. The first one would be the modifications to the four towers on the north
elevation. The applicant stated that the towers are now square off and they want to round
them off to soften them that will be treated with stucco. The lettering will be part of the
sign submittal. Discussion followed on the painting and the porcelain ceramic that is
imbedded into the stucco. Steve Amsbaugh stated that what they have, in terns of those
modifications, is an arched roof form at the top to break up the real square roof tops.
They are proposing to add some relief to the towers with some sort of a grid pattern in the
recessed area. At the junction of those triangles there will be some sort of decorative
medium applied and each one of those triangular grid patterns will be painted an
articulated preconceived color, that will be gradiated up. It will provide a transitional
effect. The whole rounding is within the logo, with the tops, in the porte cochere area, the
covers on the chimneys and the awnings. It really softens the building. Steve Amsbaugh
stated that there will be a standing rolled steel ribbed roof element on top. All of the steel
elements and the roof elements and the awnings will have the same teal gray color.
Amsbaugh stated that those are the major elements of the towers. The other elements that
relate directly to the towers would be the curved awning elements that are rolled steel in
the same color. They are approximately five foot in depth on the fascia. Those will
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
as Page 8
JEThe Seasons At Avon, Final Design Review Modifications cont
become part of the signage element in the future.
Steve Amsbaugh stated that the next important component is the enclosure of the football
area. Buz Reynolds asked if there would be wood burners. The applicant replied that
they are converting to gas. The existing area is basically a one le, el commercial building
sitting on a concrete slab on the south side of the building, separated from the
residential/commercial building. They are proposing to increase the square footage by
enclosing the football shape and also closing it at each end. Mark Donaldson described
how it would be enclosed. They are blending this roof with the existing south building's
roof so it is natural. What they are doing is removing the parapet walls so the drainage
will work. They are adding a two stop elevator from the garage to this level only. They
are zoning the parking so that what is happening is the east tower residents will be in
group F. Space will not be reserved so they are zoning it. They obviously have to have
some areas for the residential.
Steve Amsbaugh pointed out the area where they are seeking to add the roof. They will
remove the fascia. In the future they will come back with some skylight details.
Steve Amsbaugh stated that the next element is the chimney cap element. The fireplaces
will be converted to gas. The base of the fireplace will be the common brick.
The porte cochere is the next element to be changed. It is over the recently paved heated
driveway. Some of the important elements of the porte cochere is the existing concrete
retaining wall and the applicant needs to address detail as a landscape element and site
element as well as part of the building. So they will probably be back with something on
the wall. Reynolds asked if they were keeping the landscape plan that was previously
approved. The applicant responded that they will probably beef it up. Steve Amsbaugh
stated that the pone cochere canopy is proposed to be a steel metal support system that is
anchored on two stucco columns at the wall. Rhoda Schneiderman asked how they were
finished on the top. Mark Donaldson stated that they are all metal down to the stucco.
Schneiderman asked if they would be stepped. Donaldson stated they would be. It will
be the same color of the roof. The signs and fighting will be done together. Amsbaugh
stated that there is an existing rust color handrail on the back side of the porte cochere
area, along that deck that will be painted the same color and there will be a new railing
along the face of that wall. Amsbaugh stated that those are the architectural elements to
be reviewed. The most important thing is to discuss and understand the overall color
theme for the building. The seasons concept. individual architectural components, etc.
The applicants described how the towers would be handled.
SPECIAL PLANNING AND ZONING COMMISSION MEETING MINUTES
December 14, 1993
Page 9
The Seasons At Avon Final Design Review of Modifications. (cont)
Mark Donaldson stated that the main idea is to break down the massiveness of the
building. What henry Beers has done is segment the building in halves by breaking up the
middle. The applicant pointed out on the rendering the areas to be blue gray and the areas
to be red. The Commission thought it was a very creative approach.
John Perkins asked what action needs to be taken. Amsbaugh stated that Staff
recommends approval of the five items discussed tonight - the tower modifications; the
north elevation roof fascia modifications; the enclosure of the football area; the chimney
caps; the porte cochere; and the colors. There were actually six items. Amsbaugh stated
that there are three conditions to the recommendation for approval, as follows:
1. That the streetscape along Benchmark Road and the landscape improvements along the
north side of the building be incorporated into a revised site improvement plan.
2. The west building elevation be revised to soften the current large blank stucco
appearance.
3. All surface on-site parking be identified on a revised site improvement plan. All
surface parking shali be striped to clearly delineate the amount and location of surface
parking.
The applicant stated that the area of the west wall will be a day care center so there will be
basically a window detail there.
Rhoda Schneiderman moved to grant approval for items 1, 2, 3, 4, 5, and 6, and staff
recommendations 1, 2, and 3 be included.
Patti Dixon seconded and the motion carried unanimously.
The meeting was then adjourned.
Respectfully submitted,
/r
<�ve?') ICA
Charlette Pascuzzi
Recording Secretary