III. Additions and Amendments to the Agenda
Item A, the final design plan for Lot 52, Block 1, Wildridge was moved to the consent agenda. A
detail for Lot C, Phase 1 B, Office Building was submitted for review under other business.
IV. Conflicts of Interest
Commissioner Karow had a conflict with the special review use for Lot 37, Block 1, BMBC.
Commissioner Macik with conditions of Final Design for Lot 67/68, Block 1, BMBC (Petro Hut
colors).
V. Consent Agenda
The Meeting Minutes from the October 1, 2002 Planning & Zoning Commission were approved
unanimously. The Lot C, Phase 1 B Canopy detail was added the consent agenda, as well as
Item B (Colors and mockup for Lot 67/68, Block 1, BMBC, Petro Hut), and Item A under Final
Design, Lot 52, Block 1, Wildridge was added. Commissioner Wolfe moved to approve,
Commissioner Him seconded. Motion carried 5 to 0, with Commissioner Him abstaining from
approval of the minutes.
VI. Final Design Plans
A. Lot 52, Block 1, Wildridge
Duplex Home
Applicant: Scharpf Construction
This item was moved to the consent agenda for approval.
VII. Special Review Use (Public Hearing)
A. Lot 37, Block 1, Benchmark at Beaver Creek Subdivision
Auto Body Repair Shop
Applicant: Dowling's Auto Body, Inc.
Staff began the hearing with a brief presentation including a quick review of the site tour
conducted today at noon and the letter submitted by the applicant, Mike Dowling, to install
permanent fencing between this project site and the open space which is currently being used
for parking. Mike also described his desire to continue to use Bay 3 for the use which was
previously approved and utilized by Madieros, and to use Bay 4 for some parking.
Mike Dowling suggested that there were actually 21.4 parking spaces on site, and that the
parking in front of the garage doors should be counted for a total of
21 parking spaces. Mike suggested that our application will utilize Bay 3 for automotive repair,
and that Bays 1 and 2 are also being used for Valley Automotive. Mike also said that Valley
Automotive is grand -fathered in and so should their use of Bay 3. Mike said that under the
service station standards at 2/1000 square feet he meets that parking standard requirements.
Some of the services have been taken to Eagle, and they would rather utilize the parking at
Avon Autobody and simply use this site for overflow. Mike noted the illegal parking, and said
that building the fence along the open space property that the parking use has been eliminated.
Mike said he is confused with the parking standards, and does not understand how the
standards are applied. He said that any parking problems on this site can be alleviated with the
Avon Auto Body site, since there are about 50 spaces available there. The original owner made
the application for all three units at the same time.
The hearing was opened for public comment. Terry Arch, the owner for Valley Automotive, said
that he originally received approval for the three units, and choose only to use the first two,
allowing Mike Dowling to utilize the third bay. He said that he is not parking in the back of the
property, and to comply with this arrangement, he must limit his business. He said that
Dowling's generates an enormous amount of parking with his regular flood restoration service.
He did say that his customers cannot enter the parking lot in the mornings and evenings, since
the volume of traffic is so great. Dowling's has about 9 employees in the office, including his
mechanics, and is wondering where they will park. He said his employees are forced to
carpool. Terry spoke to Eric Johnson, and said that Eric told him the Town would review
parking carefully before approving another similar use.
Patrick Saenz, general manager for Dowling's, said that traffic is generated from both
operations on site, including Avon Automotive. He did say that they were issues with tow trucks
in the morning for Valley Automotive, and said that there were some issues with parked cars
from mini -storage and several cars parked along Metcalf that belong to Valley Automotive
mechanics. He did say that they are trying to alleviate the parking of towed cars with where
they are towed to, using the Texaco in West Vail and some other site in Gypsum. He did say
that they have tried to alleviate parking through some of their other sites being utilized.
Seeing as there was no further public comment, Chairman Evans closed public comment.
Commissioner deliberations began with the Chairman saying that the original approval for the
first three bays was also contingent upon the use of Avon Auto Body site at Lot 11 being used
for all pick up and delivery of automobiles. Commissioner Wolfe suggested that all cars be
delivered only to the Avon Auto Body site, and that only after they are mechanical.
Commissioner Macik asked staff what the original uses were in these units. Mike Dowling said
that he has moved all the flood restoration vehicles to other sites day and night. Commissioner
Macik said that he does not have a problem with utilizing this site as a warehouse and workshop
only, bringing only mobile vehicles to this site. Commissioner Him said that he would require
employee vehicles to park at Avon Auto Body site if he would approve this project. Mike said
that he would only utilize 3 spaces during the day. Commissioner Smith said that she could
support the use of bays 3 and 4 as only for repair. Mike Dowling said that he uses Bay 5 for
oriental carpet repair work only.
Chairman Evans said that the Town utilized 2/1000 for spaces in the past, and that we should
use it now. He did say that Mike is entitled to use the parking he has for Bays 3 and 4.
Chairman Evans said that he is in agreement with Commissioner Wolfe's suggestion that all
Minutes of PBZ Meeting
October 15, 2002
Page 2
public delivery of vehicles is to Avon Auto Body site, and not this site. Commissioner Wolfe said
that he agrees with the minimization of the issue of parking and storage on this site, and said
that this appears to be an approvable application with some conditions.
Chairman Evans said that he would allow the use with the stipulation that there is no sign up
there and that there is no active retail pickup and drop-off at that site. Commissioner Wolfe said
that spaces should be assigned by the landlord. Terry Arch did say that it was a volume issue
more than a parking issue. Mike did say that all the tow trucks would go to the Avon Auto Body
shop, and that he would try to do so.
Commissioner Wolfe mad a motion to approved the SRU for Dowling's Auto Body in Units 3 and
4 with the following conditions:
1. All signs regarding Dowling's removed from the site.
2. All vehicles to be accepted from the public will be at the Avon Auto Body site, including
deliveries.
Commissioner Smith seconded. Ruth Borne suggested that a condition of employee
parking for Bays 3 and 4 should be added regarding company trucks. Commissioner Wolfe
said that this was a landlord/tenant issue and would
go along with the condition. Commissioner Him said he was not in favor of employee
parking on site. Commissioner Wolfe said that he thinks Mike would not want to make the
situation worse than it is. Chairman Evans said that parking was in fact limited to 2 spaces.
Tambi Katieb reminded the Commission of the need to have the application reviewed in one
year to ensure compliance with the applicant's testimony and the conditions of approval, and
the chairman said he would like to add that the SRU is approved for one year. He also
added that this approval is running solely with the applicant only (Dowling's). The
amendments were all approved by the second, and the vote passed unanimously as follows:
1. All signs regarding Dowling's removed from the site.
2. All vehicles to be accepted from the public will be at the Avon Auto Body site, including
deliveries.
3. All employee of bays 3 and 4 park off-site
4. This SRU approval is specifically for Dowling's Auto Body
5. This SRU will require renewal in one-year from the Commission and that that renewal
will not be unduly withheld.
VIII. Conditions of Final Design
A. Lot 67/68, Block 1, Benchmark at Beaver Creek Subdivision
Petro -Hut Mockup
Applicant: George Roberts
This item was moved to consent agenda.
IX. Other Business
A. Lot C, Phase 1B, Office Building Details.
This item was moved to consent agenda.
Minutes of P&Z Meeting
October 15, 2002
Page 3
Chairman Evans asked that we pull the Barrancas project approvals, and review the final design
conditions of approval to ensure that the building is being constructed in accordance to the
approval, in particularly the rock walls and the roof element. Staff said they would review this
item. Several updates were given by staff regarding various construction projects in Town.
X. Adjourn
Commissioner Karow made a motion, with Commissioner Him seconding to adjourn and the
motion was approved unanimously. The meeting was adjourned at 7:30 PM.